Cavalli Casa Tower construction progress

Cavalli Casa Tower in Site A was registered to complete in September 2025 and is still under construction. At the last site inspection, in July 2026, it was 85% built. The developer is Zenica Property Development.

85%

Built, at the site inspection of 15 July 2026

14 months past its registered completion date

Registered completion date
September 2025
Finish at recent pace
January 2027
Construction started
November 2021
First registered
September 2021
Developer
Zenica Property Development
Community
Site A
Units
441
Escrow bank
Emirates NBD
Name in Arabic
كفالي كازا تاور
Project number
2283
Site inspections
12

Schedule

Cavalli Casa Tower was registered to complete in September 2025, 14 months ago, and is still under construction. Over the last year of inspections it has added about 2.6 points a month. Kept at that rate, the site would reach 100% around January 2027.

0%25%50%75%100%20222023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 July 2026

85%+12 pts

  • Cavalli Casa Tower construction site, inspection photo 1, 15 July 2026
  • Cavalli Casa Tower construction site, inspection photo 2, 15 July 2026
  • Cavalli Casa Tower construction site, inspection photo 3, 15 July 2026
  • Cavalli Casa Tower construction site, inspection photo 4, 15 July 2026

24 March 2026

73%+8.0 pts

  • Cavalli Casa Tower construction site, inspection photo 1, 24 March 2026
  • Cavalli Casa Tower construction site, inspection photo 2, 24 March 2026
  • Cavalli Casa Tower construction site, inspection photo 3, 24 March 2026
  • Cavalli Casa Tower construction site, inspection photo 4, 24 March 2026

24 November 2025

66%+7.5 pts

  • Cavalli Casa Tower construction site, inspection photo 1, 24 November 2025
  • Cavalli Casa Tower construction site, inspection photo 2, 24 November 2025
  • Cavalli Casa Tower construction site, inspection photo 3, 24 November 2025
  • Cavalli Casa Tower construction site, inspection photo 4, 24 November 2025

7 July 2025

58%+16 pts

  • Cavalli Casa Tower construction site, inspection photo 1, 7 July 2025
  • Cavalli Casa Tower construction site, inspection photo 2, 7 July 2025
  • Cavalli Casa Tower construction site, inspection photo 3, 7 July 2025
  • Cavalli Casa Tower construction site, inspection photo 4, 7 July 2025

20 January 2025

42%+9.2 pts

  • Cavalli Casa Tower construction site, inspection photo 1, 20 January 2025
  • Cavalli Casa Tower construction site, inspection photo 2, 20 January 2025
  • Cavalli Casa Tower construction site, inspection photo 3, 20 January 2025
  • Cavalli Casa Tower construction site, inspection photo 4, 20 January 2025

10 September 2024

32%+11 pts

  • Cavalli Casa Tower construction site, inspection photo 1, 10 September 2024
  • Cavalli Casa Tower construction site, inspection photo 2, 10 September 2024
  • Cavalli Casa Tower construction site, inspection photo 3, 10 September 2024
  • Cavalli Casa Tower construction site, inspection photo 4, 10 September 2024

14 March 2024

21%+9.4 pts

  • Cavalli Casa Tower construction site, inspection photo 1, 14 March 2024
  • Cavalli Casa Tower construction site, inspection photo 2, 14 March 2024
  • Cavalli Casa Tower construction site, inspection photo 3, 14 March 2024
  • Cavalli Casa Tower construction site, inspection photo 4, 14 March 2024

5 September 2023

12%+3.7 pts

  • Cavalli Casa Tower construction site, inspection photo 1, 5 September 2023
  • Cavalli Casa Tower construction site, inspection photo 2, 5 September 2023
  • Cavalli Casa Tower construction site, inspection photo 3, 5 September 2023
  • Cavalli Casa Tower construction site, inspection photo 4, 5 September 2023

5 June 2023

8.3%+1.3 pts

  • Cavalli Casa Tower construction site, inspection photo 1, 5 June 2023
  • Cavalli Casa Tower construction site, inspection photo 2, 5 June 2023
  • Cavalli Casa Tower construction site, inspection photo 3, 5 June 2023
  • Cavalli Casa Tower construction site, inspection photo 4, 5 June 2023

31 January 2023

7.0%+1.4 pts

  • Cavalli Casa Tower construction site, inspection photo 1, 31 January 2023
  • Cavalli Casa Tower construction site, inspection photo 2, 31 January 2023
  • Cavalli Casa Tower construction site, inspection photo 3, 31 January 2023
  • Cavalli Casa Tower construction site, inspection photo 4, 31 January 2023

All 100 site photos, by inspection date

Context

Site A has 3 projects under construction, 51% built on average.

Own a unit in Cavalli Casa Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Cavalli Casa Tower handover date?
The registered completion date was September 2025, and the register still lists Cavalli Casa Tower as under construction. At the pace of its recent inspections the site would reach 100% around January 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Cavalli Casa Tower?
Cavalli Casa Tower was 85% built at the site inspection on 15 July 2026. The site has been inspected 12 times since April 2022. The Land Department took 100 site photos at its inspections.
Is Cavalli Casa Tower delayed?
Yes. Its registered completion date of September 2025 has passed and the project is still listed as under construction.
Who is building Cavalli Casa Tower?
The registered developer is Zenica Property Development.
Which bank holds the escrow account for Cavalli Casa Tower?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.