Cavalli Casa Tower construction progress
Cavalli Casa Tower in Site A is 85% built at the Land Department inspection of July 2026. Developer Zenica Property Development. Completion registered for September 2025.
85%
Built, at the Land Department site inspection of 15 July 2026
12 months past its registered completion date
- Completion date (Land Department)
- September 2025
- Finish at recent pace
- January 2027
- Construction started
- November 2021
- Registered with the Land Department
- September 2021
- Developer
- Zenica Property Development
- Community
- Site A
- Units
- 441
- Escrow bank
- Emirates NBD
- Name in Arabic
- كفالي كازا تاور
- Land Department project number
- 2283
- Land Department site inspections
- 12
Schedule
Cavalli Casa Tower was registered to complete in September 2025, 12 months ago, and is still under construction. Over the last year of inspections it has added about 2.6 points a month. Kept at that rate, the site would reach 100% around January 2027.
Site inspections
15 July 2026
85%+12 pts
24 March 2026
73%+8.0 pts
24 November 2025
66%+7.5 pts
7 July 2025
58%+16 pts
20 January 2025
42%+9.2 pts
10 September 2024
32%+11 pts
14 March 2024
21%+9.4 pts
5 September 2023
12%+3.7 pts
5 June 2023
8.3%+1.3 pts
31 January 2023
7.0%+1.4 pts
Context
Site A has 3 projects under construction, 51% built on average.
Own a unit in Cavalli Casa Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Cavalli Casa Tower be completed?
- The completion date registered with the Dubai Land Department is September 2025. At the pace of its recent inspections the site would reach 100% around January 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Cavalli Casa Tower is built?
- 85%, measured at the Land Department site inspection on 15 July 2026. The Land Department engineers have inspected the site 12 times since April 2022.
- Is Cavalli Casa Tower delayed?
- Yes. Its registered completion date of September 2025 has passed and the Land Department still lists it as under construction.
- Who is building Cavalli Casa Tower?
- The registered developer is Zenica Property Development.
- Which bank holds the escrow account for Cavalli Casa Tower?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)



.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)


.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)