Iconic construction progress

The registered completion date for Iconic in Site A is February 2028. At the last site inspection, in August 2026, it was 35% built. The developer is Mered Residences Real Estate.

35%

Built, at the site inspection of 11 August 2026

Running behind its date

Registered completion date
February 2028
Finish at recent pace
November 2029
Construction started
September 2024
First registered
January 2024
Developer
Mered Residences Real Estate
Community
Site A
Units
319
Escrow bank
Mashreq Bank
Name in Arabic
ايكونك
Project number
2865
Site inspections
10

Schedule

Between September 2025 and August 2026 the site added about 1.7 points a month. At that rate it would finish around November 2029, more than three months after its registered date of February 2028.

0%25%50%75%100%20242025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 August 2026

35%+5.8 pts

  • Iconic construction site, inspection photo 1, 11 August 2026
  • Iconic construction site, inspection photo 2, 11 August 2026
  • Iconic construction site, inspection photo 3, 11 August 2026
  • Iconic construction site, inspection photo 4, 11 August 2026

30 April 2026

29%+4.7 pts

  • Iconic construction site, inspection photo 1, 30 April 2026
  • Iconic construction site, inspection photo 2, 30 April 2026
  • Iconic construction site, inspection photo 3, 30 April 2026
  • Iconic construction site, inspection photo 4, 30 April 2026

23 January 2026

24%+4.4 pts

  • Iconic construction site, inspection photo 1, 23 January 2026
  • Iconic construction site, inspection photo 2, 23 January 2026
  • Iconic construction site, inspection photo 3, 23 January 2026
  • Iconic construction site, inspection photo 4, 23 January 2026

16 September 2025

20%+3.6 pts

  • Iconic construction site, inspection photo 1, 16 September 2025
  • Iconic construction site, inspection photo 2, 16 September 2025
  • Iconic construction site, inspection photo 3, 16 September 2025
  • Iconic construction site, inspection photo 4, 16 September 2025

10 September 2025

16%+5.1 pts

  • Iconic construction site, inspection photo 1, 10 September 2025
  • Iconic construction site, inspection photo 2, 10 September 2025
  • Iconic construction site, inspection photo 3, 10 September 2025

9 May 2025

11%+2.4 pts

  • Iconic construction site, inspection photo 1, 9 May 2025
  • Iconic construction site, inspection photo 2, 9 May 2025
  • Iconic construction site, inspection photo 3, 9 May 2025

12 November 2024

8.8%+4.8 pts

  • Iconic construction site, inspection photo 1, 12 November 2024
  • Iconic construction site, inspection photo 2, 12 November 2024
  • Iconic construction site, inspection photo 3, 12 November 2024
  • Iconic construction site, inspection photo 4, 12 November 2024

27 June 2024

4.0%+3.8 pts

  • Iconic construction site, inspection photo 1, 27 June 2024
  • Iconic construction site, inspection photo 2, 27 June 2024
  • Iconic construction site, inspection photo 3, 27 June 2024
  • Iconic construction site, inspection photo 4, 27 June 2024

1 May 2024

0.2%+0.2 pts

  • Iconic construction site, inspection photo 1, 1 May 2024
  • Iconic construction site, inspection photo 2, 1 May 2024
  • Iconic construction site, inspection photo 3, 1 May 2024

7 December 2023

0%

  • Iconic construction site, inspection photo 1, 7 December 2023
  • Iconic construction site, inspection photo 2, 7 December 2023
  • Iconic construction site, inspection photo 3, 7 December 2023

All 52 site photos, by inspection date

Context

Site A has 3 projects under construction, 51% built on average.

Own a unit in Iconic?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Iconic handover date?
The registered completion date is February 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Iconic?
Iconic was 35% built at the site inspection on 11 August 2026. The site has been inspected 10 times since December 2023. The Land Department took 52 site photos at its inspections.
Is Iconic delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
Who is building Iconic?
The registered developer is Mered Residences Real Estate.
Which bank holds the escrow account for Iconic?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.