Silicon Gate 3 construction progress

The register lists Silicon Gate 3 in Silicon Oasis as complete, with a registered completion date of August 2013. Its last site inspection on record was in March 2013. The developer is Time Properties.

100%

Built, at the site inspection of 4 March 2013

Construction complete

Registered completion date
August 2013
Construction started
February 2009
First registered
November 2008
Community
Silicon Oasis
Units
124
Escrow bank
Emirates Islamic Bank
Name in Arabic
بوابة السيليكون 3
Project number
777
Site inspections
2

Schedule

The register lists Silicon Gate 3 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2010201120122013
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 March 2013

86%+12 pts

  • Silicon Gate 3 construction site, inspection photo 1, 4 March 2013
  • Silicon Gate 3 construction site, inspection photo 2, 4 March 2013
  • Silicon Gate 3 construction site, inspection photo 3, 4 March 2013
  • Silicon Gate 3 construction site, inspection photo 4, 4 March 2013

1 October 2012

74%

  • Silicon Gate 3 construction site, inspection photo 1, 1 October 2012
  • Silicon Gate 3 construction site, inspection photo 2, 1 October 2012
  • Silicon Gate 3 construction site, inspection photo 3, 1 October 2012
  • Silicon Gate 3 construction site, inspection photo 4, 1 October 2012

All 27 site photos, by inspection date

Context

Silicon Oasis has 10 projects under construction, 28% built on average.

Time Properties has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Silicon Gate 3?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Silicon Gate 3 handover date?
Construction of Silicon Gate 3 is recorded as complete, with a registered completion date of August 2013. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Silicon Gate 3?
Silicon Gate 3 was 100% built at the site inspection on 4 March 2013. The site has been inspected 2 times since October 2012. The Land Department took 27 site photos at its inspections.
Is Silicon Gate 3 delayed?
The register lists construction as complete.
Who is building Silicon Gate 3?
The registered developer is Time Properties. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Silicon Gate 3?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.