Sunset Bay Two By Imtiaz construction progress

The registered completion date for Sunset Bay Two By Imtiaz in Palm Deira is February 2027. At the last site inspection, in November 2026, it was 81% built. The developer is Imtiaz Real Estate Investment & Development.

81%

Built, at the site inspection of 4 November 2026

On pace for its date

Registered completion date
February 2027
Finish at recent pace
February 2027
Construction started
February 2025
First registered
February 2025
Community
Palm Deira
Units
66
Escrow bank
First Abu Dhabi Bank
Name in Arabic
صن ست باي تو من امتياز
Project number
3570
Site inspections
7

Schedule

Since January 2026 Sunset Bay Two By Imtiaz has added about 5.6 points a month. That puts 100% around February 2027, within three months of its registered completion date of February 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 November 2026

81%+11 pts

  • Sunset Bay Two By Imtiaz construction site, inspection photo 1, 4 November 2026
  • Sunset Bay Two By Imtiaz construction site, inspection photo 2, 4 November 2026
  • Sunset Bay Two By Imtiaz construction site, inspection photo 3, 4 November 2026
  • Sunset Bay Two By Imtiaz construction site, inspection photo 4, 4 November 2026

4 August 2026

70%+27 pts

  • Sunset Bay Two By Imtiaz construction site, inspection photo 1, 4 August 2026
  • Sunset Bay Two By Imtiaz construction site, inspection photo 2, 4 August 2026
  • Sunset Bay Two By Imtiaz construction site, inspection photo 3, 4 August 2026
  • Sunset Bay Two By Imtiaz construction site, inspection photo 4, 4 August 2026

5 May 2026

43%+17 pts

  • Sunset Bay Two By Imtiaz construction site, inspection photo 1, 5 May 2026
  • Sunset Bay Two By Imtiaz construction site, inspection photo 2, 5 May 2026
  • Sunset Bay Two By Imtiaz construction site, inspection photo 3, 5 May 2026
  • Sunset Bay Two By Imtiaz construction site, inspection photo 4, 5 May 2026

9 January 2026

26%+16 pts

  • Sunset Bay Two By Imtiaz construction site, inspection photo 1, 9 January 2026
  • Sunset Bay Two By Imtiaz construction site, inspection photo 2, 9 January 2026
  • Sunset Bay Two By Imtiaz construction site, inspection photo 3, 9 January 2026
  • Sunset Bay Two By Imtiaz construction site, inspection photo 4, 9 January 2026

8 October 2025

9.8%+4.9 pts

  • Sunset Bay Two By Imtiaz construction site, inspection photo 1, 8 October 2025
  • Sunset Bay Two By Imtiaz construction site, inspection photo 2, 8 October 2025
  • Sunset Bay Two By Imtiaz construction site, inspection photo 3, 8 October 2025
  • Sunset Bay Two By Imtiaz construction site, inspection photo 4, 8 October 2025

12 June 2025

4.9%+4.9 pts

  • Sunset Bay Two By Imtiaz construction site, inspection photo 1, 12 June 2025
  • Sunset Bay Two By Imtiaz construction site, inspection photo 2, 12 June 2025
  • Sunset Bay Two By Imtiaz construction site, inspection photo 3, 12 June 2025

18 February 2025

0%

  • Sunset Bay Two By Imtiaz construction site, inspection photo 1, 18 February 2025
  • Sunset Bay Two By Imtiaz construction site, inspection photo 2, 18 February 2025

All 51 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Imtiaz Real Estate Investment & Development has 11 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Sunset Bay Two By Imtiaz?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sunset Bay Two By Imtiaz handover date?
The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sunset Bay Two By Imtiaz?
Sunset Bay Two By Imtiaz was 81% built at the site inspection on 4 November 2026. The site has been inspected 7 times since February 2025. The Land Department took 51 site photos at its inspections.
Is Sunset Bay Two By Imtiaz delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of February 2027.
Who is building Sunset Bay Two By Imtiaz?
The registered developer is Imtiaz Real Estate Investment & Development. It has 10 other projects under construction in Dubai.
Which bank holds the escrow account for Sunset Bay Two By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.