Sunset Bay Three By Imtiaz construction progress

The registered completion date for Sunset Bay Three By Imtiaz in Palm Deira is March 2027. At the last site inspection, in September 2026, it was 60% built. The developer is Imtiaz Sunset Real Estate Development.

60%

Built, at the site inspection of 17 September 2026

On pace for its date

Registered completion date
March 2027
Finish at recent pace
May 2027
Construction started
March 2025
First registered
April 2025
Community
Palm Deira
Units
63
Escrow bank
First Abu Dhabi Bank
Name in Arabic
صن سيت باي ثري من امتياز
Project number
3604
Site inspections
7

Schedule

Since September 2025 Sunset Bay Three By Imtiaz has added about 4.8 points a month. That puts 100% around May 2027, within three months of its registered completion date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 September 2026

60%+22 pts

  • Sunset Bay Three By Imtiaz construction site, inspection photo 1, 17 September 2026
  • Sunset Bay Three By Imtiaz construction site, inspection photo 2, 17 September 2026
  • Sunset Bay Three By Imtiaz construction site, inspection photo 3, 17 September 2026
  • Sunset Bay Three By Imtiaz construction site, inspection photo 4, 17 September 2026

25 June 2026

38%+16 pts

  • Sunset Bay Three By Imtiaz construction site, inspection photo 1, 25 June 2026
  • Sunset Bay Three By Imtiaz construction site, inspection photo 2, 25 June 2026
  • Sunset Bay Three By Imtiaz construction site, inspection photo 3, 25 June 2026
  • Sunset Bay Three By Imtiaz construction site, inspection photo 4, 25 June 2026

23 March 2026

23%+8.5 pts

  • Sunset Bay Three By Imtiaz construction site, inspection photo 1, 23 March 2026
  • Sunset Bay Three By Imtiaz construction site, inspection photo 2, 23 March 2026
  • Sunset Bay Three By Imtiaz construction site, inspection photo 3, 23 March 2026
  • Sunset Bay Three By Imtiaz construction site, inspection photo 4, 23 March 2026

30 December 2025

14%+9.9 pts

  • Sunset Bay Three By Imtiaz construction site, inspection photo 1, 30 December 2025
  • Sunset Bay Three By Imtiaz construction site, inspection photo 2, 30 December 2025
  • Sunset Bay Three By Imtiaz construction site, inspection photo 3, 30 December 2025
  • Sunset Bay Three By Imtiaz construction site, inspection photo 4, 30 December 2025

30 September 2025

4.3%+3.9 pts

  • Sunset Bay Three By Imtiaz construction site, inspection photo 1, 30 September 2025
  • Sunset Bay Three By Imtiaz construction site, inspection photo 2, 30 September 2025
  • Sunset Bay Three By Imtiaz construction site, inspection photo 3, 30 September 2025
  • Sunset Bay Three By Imtiaz construction site, inspection photo 4, 30 September 2025

12 June 2025

0.4%+0.4 pts

  • Sunset Bay Three By Imtiaz construction site, inspection photo 1, 12 June 2025
  • Sunset Bay Three By Imtiaz construction site, inspection photo 2, 12 June 2025
  • Sunset Bay Three By Imtiaz construction site, inspection photo 3, 12 June 2025
  • Sunset Bay Three By Imtiaz construction site, inspection photo 4, 12 June 2025

11 March 2025

0%

  • Sunset Bay Three By Imtiaz construction site, inspection photo 1, 11 March 2025
  • Sunset Bay Three By Imtiaz construction site, inspection photo 2, 11 March 2025

All 42 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Imtiaz Sunset Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sunset Bay Three By Imtiaz?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sunset Bay Three By Imtiaz handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sunset Bay Three By Imtiaz?
Sunset Bay Three By Imtiaz was 60% built at the site inspection on 17 September 2026. The site has been inspected 7 times since March 2025. The Land Department took 42 site photos at its inspections.
Is Sunset Bay Three By Imtiaz delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2027.
Who is building Sunset Bay Three By Imtiaz?
The registered developer is Imtiaz Sunset Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Sunset Bay Three By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.