42 photos from 7 site inspections, newest first. The percentage is how much of Sunset Bay Three By Imtiaz was built on the day of each visit.

17 September 202660% built

25 June 202638% built

23 March 202623% built

30 December 202514% built

30 September 20254.3% built

12 June 20250.4% built

11 March 20250% built

Back to Sunset Bay Three By Imtiaz construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.