Sunset Bay Four By Imtiaz construction progress

Sunset Bay Four By Imtiaz in Palm Deira is 53% built at the Land Department inspection of September 2026. Developer Imtiaz Sunset Real Estate Development. Completion registered for May 2027.

53%

Built, at the Land Department site inspection of 29 September 2026

Running behind its date

Completion date (Land Department)
May 2027
Finish at recent pace
August 2027
Construction started
May 2025
Registered with the Land Department
May 2025
Community
Palm Deira
Units
63
Escrow bank
First Abu Dhabi Bank
Name in Arabic
صن سيت باي فور من امتياز
Land Department project number
3714
Land Department site inspections
6

Schedule

Between December 2025 and September 2026 the site added about 4.5 points a month. At that rate it would finish around August 2027, more than three months after the May 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

29 September 2026

53%+16 pts

  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 1, 29 September 2026
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 2, 29 September 2026
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 3, 29 September 2026
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 4, 29 September 2026

24 June 2026

37%+18 pts

  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 1, 24 June 2026
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 2, 24 June 2026
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 3, 24 June 2026
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 4, 24 June 2026

23 March 2026

20%+6.9 pts

  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 1, 23 March 2026
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 2, 23 March 2026
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 3, 23 March 2026
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 4, 23 March 2026

30 December 2025

13%+11 pts

  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 1, 30 December 2025
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 2, 30 December 2025
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 3, 30 December 2025
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 4, 30 December 2025

6 August 2025

2.0%+2.0 pts

  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 1, 6 August 2025
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 2, 6 August 2025
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 3, 6 August 2025
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 4, 6 August 2025

24 April 2025

0%

  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 1, 24 April 2025
  • Sunset Bay Four By Imtiaz construction site, Land Department inspection photo 2, 24 April 2025

All 34 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Imtiaz Sunset Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sunset Bay Four By Imtiaz?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Sunset Bay Four By Imtiaz be completed?
The completion date registered with the Dubai Land Department is May 2027. At the pace of its recent inspections the site would reach 100% around August 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Sunset Bay Four By Imtiaz is built?
53%, measured at the Land Department site inspection on 29 September 2026. The Land Department engineers have inspected the site 6 times since April 2025.
Is Sunset Bay Four By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
Who is building Sunset Bay Four By Imtiaz?
The registered developer is Imtiaz Sunset Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Sunset Bay Four By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.