Sunset Bay Four By Imtiaz construction progress
The registered completion date for Sunset Bay Four By Imtiaz in Palm Deira is May 2027. At the last site inspection, in September 2026, it was 53% built. The developer is Imtiaz Sunset Real Estate Development.
53%
Built, at the site inspection of 29 September 2026
Running behind its date
- Registered completion date
- May 2027
- Finish at recent pace
- August 2027
- Construction started
- May 2025
- First registered
- May 2025
- Community
- Palm Deira
- Units
- 63
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- صن سيت باي فور من امتياز
- Project number
- 3714
- Site inspections
- 6
Schedule
Between December 2025 and September 2026 the site added about 4.5 points a month. At that rate it would finish around August 2027, more than three months after its registered date of May 2027.
Site inspections
29 September 2026
53%+16 pts
24 June 2026
37%+18 pts
23 March 2026
20%+6.9 pts
30 December 2025
13%+11 pts
6 August 2025
2.0%+2.0 pts
24 April 2025
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Imtiaz Sunset Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Sunset Bay Four By Imtiaz?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Sunset Bay Four By Imtiaz handover date?
- The registered completion date is May 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Sunset Bay Four By Imtiaz?
- Sunset Bay Four By Imtiaz was 53% built at the site inspection on 29 September 2026. The site has been inspected 6 times since April 2025. The Land Department took 34 site photos at its inspections.
- Is Sunset Bay Four By Imtiaz delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
- Who is building Sunset Bay Four By Imtiaz?
- The registered developer is Imtiaz Sunset Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Sunset Bay Four By Imtiaz?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sunset Bay One By ImtiazAlso by Imtiaz Sunset Real Estate Development. 94%, Due December 2026.
- Sunset Bay Three By ImtiazAlso by Imtiaz Sunset Real Estate Development. 60%, Due March 2027.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.