Sunset Bay One By Imtiaz construction progress
Sunset Bay One By Imtiaz in Palm Deira is 78% built at the Land Department inspection of August 2026. Developer Imtiaz Sunset Real Estate Development. Completion registered for December 2026.
78%
Built, at the Land Department site inspection of 4 August 2026
On pace for its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- December 2026
- Construction started
- December 2024
- Registered with the Land Department
- January 2025
- Community
- Palm Deira
- Units
- 66
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- صن ست باي وان من امتياز
- Land Department project number
- 3460
- Land Department site inspections
- 7
Schedule
Since October 2025 Sunset Bay One By Imtiaz has added about 5.5 points a month. That puts 100% around December 2026, within three months of its registered completion date of December 2026.
Site inspections
4 August 2026
78%+14 pts
11 May 2026
64%+22 pts
13 February 2026
42%+14 pts
31 October 2025
28%+15 pts
2 August 2025
13%+7.0 pts
23 April 2025
5.9%+5.9 pts
18 December 2024
0%
Context
Palm Deira has 95 projects under construction, 22% built on average. Sunset Bay One By Imtiaz is ahead of that average.
Imtiaz Sunset Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Sunset Bay One By Imtiaz?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Sunset Bay One By Imtiaz be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around December 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Sunset Bay One By Imtiaz is built?
- 78%, measured at the Land Department site inspection on 4 August 2026. The Land Department engineers have inspected the site 7 times since December 2024.
- Is Sunset Bay One By Imtiaz delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
- Who is building Sunset Bay One By Imtiaz?
- The registered developer is Imtiaz Sunset Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Sunset Bay One By Imtiaz?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sunset Bay Three By ImtiazAlso by Imtiaz Sunset Real Estate Development. 60%, Due March 2027.
- Sunset Bay Four By ImtiazAlso by Imtiaz Sunset Real Estate Development. 53%, Due May 2027.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)