Sunset Bay One By Imtiaz construction progress
The registered completion date for Sunset Bay One By Imtiaz in Palm Deira is December 2026. At the last site inspection, in November 2026, it was 94% built. The developer is Imtiaz Sunset Real Estate Development.
94%
Built, at the site inspection of 2 November 2026
On pace for its date
- Registered completion date
- December 2026
- Finish at recent pace
- December 2026
- Construction started
- December 2024
- First registered
- January 2025
- Community
- Palm Deira
- Units
- 66
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- صن ست باي وان من امتياز
- Project number
- 3460
- Site inspections
- 8
Schedule
Since February 2026 Sunset Bay One By Imtiaz has added about 6.0 points a month. That puts 100% around December 2026, within three months of its registered completion date of December 2026.
Site inspections
2 November 2026
94%+15 pts
4 August 2026
78%+14 pts
11 May 2026
64%+22 pts
13 February 2026
42%+14 pts
31 October 2025
28%+15 pts
2 August 2025
13%+7.0 pts
23 April 2025
5.9%+5.9 pts
18 December 2024
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Imtiaz Sunset Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Sunset Bay One By Imtiaz?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Sunset Bay One By Imtiaz handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Sunset Bay One By Imtiaz?
- Sunset Bay One By Imtiaz was 94% built at the site inspection on 2 November 2026. The site has been inspected 8 times since December 2024. The Land Department took 48 site photos at its inspections.
- Is Sunset Bay One By Imtiaz delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
- Who is building Sunset Bay One By Imtiaz?
- The registered developer is Imtiaz Sunset Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Sunset Bay One By Imtiaz?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sunset Bay Three By ImtiazAlso by Imtiaz Sunset Real Estate Development. 60%, Due March 2027.
- Sunset Bay Four By ImtiazAlso by Imtiaz Sunset Real Estate Development. 53%, Due May 2027.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)