Sunset Bay One By Imtiaz construction progress

The registered completion date for Sunset Bay One By Imtiaz in Palm Deira is December 2026. At the last site inspection, in November 2026, it was 94% built. The developer is Imtiaz Sunset Real Estate Development.

94%

Built, at the site inspection of 2 November 2026

On pace for its date

Registered completion date
December 2026
Finish at recent pace
December 2026
Construction started
December 2024
First registered
January 2025
Community
Palm Deira
Units
66
Escrow bank
First Abu Dhabi Bank
Name in Arabic
صن ست باي وان من امتياز
Project number
3460
Site inspections
8

Schedule

Since February 2026 Sunset Bay One By Imtiaz has added about 6.0 points a month. That puts 100% around December 2026, within three months of its registered completion date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 November 2026

94%+15 pts

  • Sunset Bay One By Imtiaz construction site, inspection photo 1, 2 November 2026
  • Sunset Bay One By Imtiaz construction site, inspection photo 2, 2 November 2026
  • Sunset Bay One By Imtiaz construction site, inspection photo 3, 2 November 2026
  • Sunset Bay One By Imtiaz construction site, inspection photo 4, 2 November 2026

4 August 2026

78%+14 pts

  • Sunset Bay One By Imtiaz construction site, inspection photo 1, 4 August 2026
  • Sunset Bay One By Imtiaz construction site, inspection photo 2, 4 August 2026
  • Sunset Bay One By Imtiaz construction site, inspection photo 3, 4 August 2026
  • Sunset Bay One By Imtiaz construction site, inspection photo 4, 4 August 2026

11 May 2026

64%+22 pts

  • Sunset Bay One By Imtiaz construction site, inspection photo 1, 11 May 2026
  • Sunset Bay One By Imtiaz construction site, inspection photo 2, 11 May 2026
  • Sunset Bay One By Imtiaz construction site, inspection photo 3, 11 May 2026
  • Sunset Bay One By Imtiaz construction site, inspection photo 4, 11 May 2026

13 February 2026

42%+14 pts

  • Sunset Bay One By Imtiaz construction site, inspection photo 1, 13 February 2026
  • Sunset Bay One By Imtiaz construction site, inspection photo 2, 13 February 2026
  • Sunset Bay One By Imtiaz construction site, inspection photo 3, 13 February 2026
  • Sunset Bay One By Imtiaz construction site, inspection photo 4, 13 February 2026

31 October 2025

28%+15 pts

  • Sunset Bay One By Imtiaz construction site, inspection photo 1, 31 October 2025
  • Sunset Bay One By Imtiaz construction site, inspection photo 2, 31 October 2025
  • Sunset Bay One By Imtiaz construction site, inspection photo 3, 31 October 2025
  • Sunset Bay One By Imtiaz construction site, inspection photo 4, 31 October 2025

2 August 2025

13%+7.0 pts

  • Sunset Bay One By Imtiaz construction site, inspection photo 1, 2 August 2025
  • Sunset Bay One By Imtiaz construction site, inspection photo 2, 2 August 2025
  • Sunset Bay One By Imtiaz construction site, inspection photo 3, 2 August 2025
  • Sunset Bay One By Imtiaz construction site, inspection photo 4, 2 August 2025

23 April 2025

5.9%+5.9 pts

  • Sunset Bay One By Imtiaz construction site, inspection photo 1, 23 April 2025
  • Sunset Bay One By Imtiaz construction site, inspection photo 2, 23 April 2025
  • Sunset Bay One By Imtiaz construction site, inspection photo 3, 23 April 2025

18 December 2024

0%

  • Sunset Bay One By Imtiaz construction site, inspection photo 1, 18 December 2024
  • Sunset Bay One By Imtiaz construction site, inspection photo 2, 18 December 2024

All 48 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Imtiaz Sunset Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sunset Bay One By Imtiaz?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sunset Bay One By Imtiaz handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sunset Bay One By Imtiaz?
Sunset Bay One By Imtiaz was 94% built at the site inspection on 2 November 2026. The site has been inspected 8 times since December 2024. The Land Department took 48 site photos at its inspections.
Is Sunset Bay One By Imtiaz delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
Who is building Sunset Bay One By Imtiaz?
The registered developer is Imtiaz Sunset Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Sunset Bay One By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.