Edgewater Residences 3 construction progress

The registered completion date for Edgewater Residences 3 in Palm Deira is January 2027. At the last site inspection, in August 2026, it was 30% built. The developer is M G S Development.

30%

Built, at the site inspection of 31 August 2026

Running behind its date

Registered completion date
January 2027
Finish at recent pace
October 2028
Construction started
November 2024
First registered
March 2025
Community
Palm Deira
Units
328
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
مساكن ايدج ووتر 3
Project number
3177
Site inspections
5

Schedule

Between December 2025 and August 2026 the site added about 2.7 points a month. At that rate it would finish around October 2028, more than three months after its registered date of January 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

31 August 2026

30%+15 pts

  • Edgewater Residences 3 construction site, inspection photo 1, 31 August 2026
  • Edgewater Residences 3 construction site, inspection photo 2, 31 August 2026
  • Edgewater Residences 3 construction site, inspection photo 3, 31 August 2026
  • Edgewater Residences 3 construction site, inspection photo 4, 31 August 2026

4 May 2026

15%+6.5 pts

  • Edgewater Residences 3 construction site, inspection photo 1, 4 May 2026
  • Edgewater Residences 3 construction site, inspection photo 2, 4 May 2026
  • Edgewater Residences 3 construction site, inspection photo 3, 4 May 2026
  • Edgewater Residences 3 construction site, inspection photo 4, 4 May 2026

27 December 2025

8.5%+3.3 pts

  • Edgewater Residences 3 construction site, inspection photo 1, 27 December 2025
  • Edgewater Residences 3 construction site, inspection photo 2, 27 December 2025
  • Edgewater Residences 3 construction site, inspection photo 3, 27 December 2025
  • Edgewater Residences 3 construction site, inspection photo 4, 27 December 2025

15 July 2025

5.2%+5.2 pts

  • Edgewater Residences 3 construction site, inspection photo 1, 15 July 2025
  • Edgewater Residences 3 construction site, inspection photo 2, 15 July 2025
  • Edgewater Residences 3 construction site, inspection photo 3, 15 July 2025
  • Edgewater Residences 3 construction site, inspection photo 4, 15 July 2025

10 February 2025

0%

  • Edgewater Residences 3 construction site, inspection photo 1, 10 February 2025
  • Edgewater Residences 3 construction site, inspection photo 2, 10 February 2025

All 28 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

M G S Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Edgewater Residences 3?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Edgewater Residences 3 handover date?
The registered completion date is January 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Edgewater Residences 3?
Edgewater Residences 3 was 30% built at the site inspection on 31 August 2026. The site has been inspected 5 times since February 2025. The Land Department took 28 site photos at its inspections.
Is Edgewater Residences 3 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
Who is building Edgewater Residences 3?
The registered developer is M G S Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Edgewater Residences 3?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.