Edgewater Residences 2 construction progress

Edgewater Residences 2 in Palm Deira is 55% built at the Land Department inspection of August 2026. Developer M G S Development. Completion registered for August 2026.

55%

Built, at the Land Department site inspection of 31 August 2026

1 months past its registered completion date

Completion date (Land Department)
August 2026
Finish at recent pace
September 2027
Construction started
June 2024
Registered with the Land Department
June 2024
Community
Palm Deira
Units
97
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
مساكن ايدج ووتر 2
Land Department project number
3011
Land Department site inspections
6

Schedule

Edgewater Residences 2 was registered to complete in August 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 3.7 points a month. Kept at that rate, the site would reach 100% around September 2027.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

31 August 2026

55%+17 pts

  • Edgewater Residences 2 construction site, Land Department inspection photo 1, 31 August 2026
  • Edgewater Residences 2 construction site, Land Department inspection photo 2, 31 August 2026
  • Edgewater Residences 2 construction site, Land Department inspection photo 3, 31 August 2026
  • Edgewater Residences 2 construction site, Land Department inspection photo 4, 31 August 2026

28 April 2026

38%+17 pts

  • Edgewater Residences 2 construction site, Land Department inspection photo 1, 28 April 2026
  • Edgewater Residences 2 construction site, Land Department inspection photo 2, 28 April 2026
  • Edgewater Residences 2 construction site, Land Department inspection photo 3, 28 April 2026
  • Edgewater Residences 2 construction site, Land Department inspection photo 4, 28 April 2026

27 November 2025

21%+7.9 pts

  • Edgewater Residences 2 construction site, Land Department inspection photo 1, 27 November 2025
  • Edgewater Residences 2 construction site, Land Department inspection photo 2, 27 November 2025
  • Edgewater Residences 2 construction site, Land Department inspection photo 3, 27 November 2025
  • Edgewater Residences 2 construction site, Land Department inspection photo 4, 27 November 2025

15 July 2025

13%+12 pts

  • Edgewater Residences 2 construction site, Land Department inspection photo 1, 15 July 2025
  • Edgewater Residences 2 construction site, Land Department inspection photo 2, 15 July 2025
  • Edgewater Residences 2 construction site, Land Department inspection photo 3, 15 July 2025
  • Edgewater Residences 2 construction site, Land Department inspection photo 4, 15 July 2025

27 January 2025

0.8%+0.8 pts

  • Edgewater Residences 2 construction site, Land Department inspection photo 1, 27 January 2025
  • Edgewater Residences 2 construction site, Land Department inspection photo 2, 27 January 2025
  • Edgewater Residences 2 construction site, Land Department inspection photo 3, 27 January 2025

5 April 2024

0%

  • Edgewater Residences 2 construction site, Land Department inspection photo 1, 5 April 2024
  • Edgewater Residences 2 construction site, Land Department inspection photo 2, 5 April 2024

All 34 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

M G S Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Edgewater Residences 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Edgewater Residences 2 be completed?
The completion date registered with the Dubai Land Department is August 2026. At the pace of its recent inspections the site would reach 100% around September 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Edgewater Residences 2 is built?
55%, measured at the Land Department site inspection on 31 August 2026. The Land Department engineers have inspected the site 6 times since April 2024.
Is Edgewater Residences 2 delayed?
Yes. Its registered completion date of August 2026 has passed and the Land Department still lists it as under construction.
Who is building Edgewater Residences 2?
The registered developer is M G S Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Edgewater Residences 2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.