35 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Edgewater Residences was built on the day of each visit.

31 August 202648% built

6 April 202628% built

27 November 202516% built

15 July 20259.2% built

27 January 20252.8% built

12 February 20240% built

Back to Edgewater Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.