Beach Walk Residences 2 construction progress

The register lists Beach Walk Residences 2 in Palm Deira as complete, with a registered completion date of August 2026. Its last site inspection on record was in August 2026. The developer is Imtiaz Ghd Real Estate Development.

100%

Built, at the site inspection of 6 August 2026

Construction complete

Registered completion date
August 2026
Construction started
August 2024
First registered
August 2024
Community
Palm Deira
Units
63
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بيتش ووك ريزيدنسز 2
Project number
3224
Site inspections
9

Schedule

The register lists Beach Walk Residences 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 August 2026

100%+2.8 pts

  • Beach Walk Residences 2 construction site, inspection photo 1, 6 August 2026
  • Beach Walk Residences 2 construction site, inspection photo 2, 6 August 2026
  • Beach Walk Residences 2 construction site, inspection photo 3, 6 August 2026
  • Beach Walk Residences 2 construction site, inspection photo 4, 6 August 2026

13 July 2026

97%+7.7 pts

  • Beach Walk Residences 2 construction site, inspection photo 1, 13 July 2026
  • Beach Walk Residences 2 construction site, inspection photo 2, 13 July 2026
  • Beach Walk Residences 2 construction site, inspection photo 3, 13 July 2026
  • Beach Walk Residences 2 construction site, inspection photo 4, 13 July 2026

21 May 2026

89%+13 pts

  • Beach Walk Residences 2 construction site, inspection photo 1, 21 May 2026
  • Beach Walk Residences 2 construction site, inspection photo 2, 21 May 2026
  • Beach Walk Residences 2 construction site, inspection photo 3, 21 May 2026
  • Beach Walk Residences 2 construction site, inspection photo 4, 21 May 2026

20 February 2026

77%+9.3 pts

  • Beach Walk Residences 2 construction site, inspection photo 1, 20 February 2026
  • Beach Walk Residences 2 construction site, inspection photo 2, 20 February 2026
  • Beach Walk Residences 2 construction site, inspection photo 3, 20 February 2026
  • Beach Walk Residences 2 construction site, inspection photo 4, 20 February 2026

6 November 2025

67%+20 pts

  • Beach Walk Residences 2 construction site, inspection photo 1, 6 November 2025
  • Beach Walk Residences 2 construction site, inspection photo 2, 6 November 2025
  • Beach Walk Residences 2 construction site, inspection photo 3, 6 November 2025
  • Beach Walk Residences 2 construction site, inspection photo 4, 6 November 2025

12 August 2025

47%+13 pts

  • Beach Walk Residences 2 construction site, inspection photo 1, 12 August 2025
  • Beach Walk Residences 2 construction site, inspection photo 2, 12 August 2025
  • Beach Walk Residences 2 construction site, inspection photo 3, 12 August 2025
  • Beach Walk Residences 2 construction site, inspection photo 4, 12 August 2025

29 May 2025

35%+24 pts

  • Beach Walk Residences 2 construction site, inspection photo 1, 29 May 2025
  • Beach Walk Residences 2 construction site, inspection photo 2, 29 May 2025
  • Beach Walk Residences 2 construction site, inspection photo 3, 29 May 2025
  • Beach Walk Residences 2 construction site, inspection photo 4, 29 May 2025

15 January 2025

11%+11 pts

  • Beach Walk Residences 2 construction site, inspection photo 1, 15 January 2025
  • Beach Walk Residences 2 construction site, inspection photo 2, 15 January 2025
  • Beach Walk Residences 2 construction site, inspection photo 3, 15 January 2025
  • Beach Walk Residences 2 construction site, inspection photo 4, 15 January 2025

15 August 2024

0%

  • Beach Walk Residences 2 construction site, inspection photo 1, 15 August 2024
  • Beach Walk Residences 2 construction site, inspection photo 2, 15 August 2024

All 83 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Imtiaz Ghd Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Beach Walk Residences 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Beach Walk Residences 2 handover date?
Construction of Beach Walk Residences 2 is recorded as complete, with a registered completion date of August 2026. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Beach Walk Residences 2?
Beach Walk Residences 2 was 100% built at the site inspection on 6 August 2026. The site has been inspected 9 times since August 2024. The Land Department took 83 site photos at its inspections.
Is Beach Walk Residences 2 delayed?
The register lists construction as complete.
Who is building Beach Walk Residences 2?
The registered developer is Imtiaz Ghd Real Estate Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Beach Walk Residences 2?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.