Cotier House 1 By Imtiaz construction progress
Cotier House 1 By Imtiaz in Palm Deira is 43% built at the Land Department inspection of August 2026. Developer Imtiaz Ghd Real Estate Development. Completion registered for January 2027.
43%
Built, at the Land Department site inspection of 14 August 2026
Running behind its date
- Completion date (Land Department)
- January 2027
- Finish at recent pace
- February 2028
- Construction started
- January 2025
- Registered with the Land Department
- February 2025
- Developer
- Imtiaz Ghd Real Estate Development
- Community
- Palm Deira
- Units
- 137
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- كوتير هاوس 1 من امتياز
- Land Department project number
- 3394
- Land Department site inspections
- 7
Schedule
Between September 2025 and August 2026 the site added about 3.2 points a month. At that rate it would finish around February 2028, more than three months after the January 2027 date registered with the Land Department.
Site inspections
14 August 2026
43%+14 pts
3 June 2026
29%+8.0 pts
23 March 2026
21%+6.9 pts
23 December 2025
14%+6.3 pts
12 September 2025
8.1%+3.7 pts
27 May 2025
4.4%+4.4 pts
16 January 2025
0%
Context
Palm Deira has 95 projects under construction, 22% built on average.
Imtiaz Ghd Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Cotier House 1 By Imtiaz?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Cotier House 1 By Imtiaz be completed?
- The completion date registered with the Dubai Land Department is January 2027. At the pace of its recent inspections the site would reach 100% around February 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Cotier House 1 By Imtiaz is built?
- 43%, measured at the Land Department site inspection on 14 August 2026. The Land Department engineers have inspected the site 7 times since January 2025.
- Is Cotier House 1 By Imtiaz delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
- Who is building Cotier House 1 By Imtiaz?
- The registered developer is Imtiaz Ghd Real Estate Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Cotier House 1 By Imtiaz?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Beach Walk Grand 2 By ImtiazAlso by Imtiaz Ghd Real Estate Development. 24%, Due December 2027.
- Sunset Bay Grand By ImtiazAlso by Imtiaz Ghd Real Estate Development. 16%.
- Chavelle By ImtiazAlso by Imtiaz Ghd Real Estate Development. 0%, Due March 2029.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)