Sunset Bay Grand By Imtiaz construction progress

The registered completion date for Sunset Bay Grand By Imtiaz in Palm Deira is February 2028. At the last site inspection, in November 2026, it was 23% built. The developer is Imtiaz Ghd Real Estate Development.

23%

Built, at the site inspection of 9 November 2026

Running behind its date

Registered completion date
February 2028
Finish at recent pace
June 2030
Construction started
October 2025
First registered
September 2025
Community
Palm Deira
Units
98
Escrow bank
First Abu Dhabi Bank
Name in Arabic
صن سيت باي جراند من امتياز
Project number
3868
Site inspections
6

Schedule

Between November 2025 and November 2026 the site added about 1.8 points a month. At that rate it would finish around June 2030, more than three months after its registered date of February 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 November 2026

23%+6.8 pts

  • Sunset Bay Grand By Imtiaz construction site, inspection photo 1, 9 November 2026
  • Sunset Bay Grand By Imtiaz construction site, inspection photo 2, 9 November 2026
  • Sunset Bay Grand By Imtiaz construction site, inspection photo 3, 9 November 2026
  • Sunset Bay Grand By Imtiaz construction site, inspection photo 4, 9 November 2026

17 August 2026

16%+6.0 pts

  • Sunset Bay Grand By Imtiaz construction site, inspection photo 1, 17 August 2026
  • Sunset Bay Grand By Imtiaz construction site, inspection photo 2, 17 August 2026
  • Sunset Bay Grand By Imtiaz construction site, inspection photo 3, 17 August 2026
  • Sunset Bay Grand By Imtiaz construction site, inspection photo 4, 17 August 2026

20 May 2026

10%+6.1 pts

  • Sunset Bay Grand By Imtiaz construction site, inspection photo 1, 20 May 2026
  • Sunset Bay Grand By Imtiaz construction site, inspection photo 2, 20 May 2026
  • Sunset Bay Grand By Imtiaz construction site, inspection photo 3, 20 May 2026
  • Sunset Bay Grand By Imtiaz construction site, inspection photo 4, 20 May 2026

20 February 2026

4.2%+2.5 pts

  • Sunset Bay Grand By Imtiaz construction site, inspection photo 1, 20 February 2026
  • Sunset Bay Grand By Imtiaz construction site, inspection photo 2, 20 February 2026
  • Sunset Bay Grand By Imtiaz construction site, inspection photo 3, 20 February 2026
  • Sunset Bay Grand By Imtiaz construction site, inspection photo 4, 20 February 2026

12 November 2025

1.7%+1.7 pts

  • Sunset Bay Grand By Imtiaz construction site, inspection photo 1, 12 November 2025
  • Sunset Bay Grand By Imtiaz construction site, inspection photo 2, 12 November 2025
  • Sunset Bay Grand By Imtiaz construction site, inspection photo 3, 12 November 2025

7 July 2025

0%

  • Sunset Bay Grand By Imtiaz construction site, inspection photo 1, 7 July 2025
  • Sunset Bay Grand By Imtiaz construction site, inspection photo 2, 7 July 2025

All 30 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Imtiaz Ghd Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sunset Bay Grand By Imtiaz?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sunset Bay Grand By Imtiaz handover date?
The registered completion date is February 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sunset Bay Grand By Imtiaz?
Sunset Bay Grand By Imtiaz was 23% built at the site inspection on 9 November 2026. The site has been inspected 6 times since July 2025. The Land Department took 30 site photos at its inspections.
Is Sunset Bay Grand By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
Who is building Sunset Bay Grand By Imtiaz?
The registered developer is Imtiaz Ghd Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Sunset Bay Grand By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.