Skip to content

Beach Walk Grand 2 By Imtiaz construction progress

The registered completion date for Beach Walk Grand 2 By Imtiaz in Palm Deira is December 2027. At the last site inspection, in September 2026, it was 24% built. The developer is Imtiaz Ghd Real Estate Development.

24%

Built, at the site inspection of 14 September 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
October 2029
Construction started
July 2025
First registered
July 2025
Community
Palm Deira
Units
108
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بيتش ووك جراند 2 من امتياز
Project number
3724
Site inspections
6

Schedule

Between December 2025 and September 2026 the site added about 2.1 points a month. At that rate it would finish around October 2029, more than three months after its registered date of December 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 September 2026

24%+6.1 pts

  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 1, 14 September 2026
  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 2, 14 September 2026
  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 3, 14 September 2026
  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 4, 14 September 2026

23 June 2026

17%+9.1 pts

  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 1, 23 June 2026
  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 2, 23 June 2026
  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 3, 23 June 2026
  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 4, 23 June 2026

23 March 2026

8.4%+3.0 pts

  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 1, 23 March 2026
  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 2, 23 March 2026
  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 3, 23 March 2026
  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 4, 23 March 2026

23 December 2025

5.3%+5.2 pts

  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 1, 23 December 2025
  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 2, 23 December 2025
  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 3, 23 December 2025
  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 4, 23 December 2025

4 September 2025

0.2%+0.2 pts

  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 1, 4 September 2025
  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 2, 4 September 2025
  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 3, 4 September 2025

1 May 2025

0%

  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 1, 1 May 2025
  • Beach Walk Grand 2 By Imtiaz construction site, inspection photo 2, 1 May 2025

All 28 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Imtiaz Ghd Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Beach Walk Grand 2 By Imtiaz?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Beach Walk Grand 2 By Imtiaz handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Beach Walk Grand 2 By Imtiaz?
Beach Walk Grand 2 By Imtiaz was 24% built at the site inspection on 14 September 2026. The site has been inspected 6 times since May 2025. The Land Department took 28 site photos at its inspections.
Is Beach Walk Grand 2 By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Beach Walk Grand 2 By Imtiaz?
The registered developer is Imtiaz Ghd Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Beach Walk Grand 2 By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.