Beach Walk Grand 2 By Imtiaz construction progress

Beach Walk Grand 2 By Imtiaz in Palm Deira is 24% built at the Land Department inspection of September 2026. Developer Imtiaz Ghd Real Estate Development. Completion registered for December 2027.

24%

Built, at the Land Department site inspection of 14 September 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
October 2029
Construction started
July 2025
Registered with the Land Department
July 2025
Community
Palm Deira
Units
108
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بيتش ووك جراند 2 من امتياز
Land Department project number
3724
Land Department site inspections
6

Schedule

Between December 2025 and September 2026 the site added about 2.1 points a month. At that rate it would finish around October 2029, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 September 2026

24%+6.1 pts

  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 1, 14 September 2026
  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 2, 14 September 2026
  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 3, 14 September 2026
  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 4, 14 September 2026

23 June 2026

17%+9.1 pts

  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 1, 23 June 2026
  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 2, 23 June 2026
  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 3, 23 June 2026
  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 4, 23 June 2026

23 March 2026

8.4%+3.0 pts

  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 1, 23 March 2026
  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 2, 23 March 2026
  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 3, 23 March 2026
  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 4, 23 March 2026

23 December 2025

5.3%+5.2 pts

  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 1, 23 December 2025
  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 2, 23 December 2025
  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 3, 23 December 2025
  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 4, 23 December 2025

4 September 2025

0.2%+0.2 pts

  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 1, 4 September 2025
  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 2, 4 September 2025
  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 3, 4 September 2025

1 May 2025

0%

  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 1, 1 May 2025
  • Beach Walk Grand 2 By Imtiaz construction site, Land Department inspection photo 2, 1 May 2025

All 28 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Imtiaz Ghd Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Beach Walk Grand 2 By Imtiaz?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Beach Walk Grand 2 By Imtiaz be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around October 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Beach Walk Grand 2 By Imtiaz is built?
24%, measured at the Land Department site inspection on 14 September 2026. The Land Department engineers have inspected the site 6 times since May 2025.
Is Beach Walk Grand 2 By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Beach Walk Grand 2 By Imtiaz?
The registered developer is Imtiaz Ghd Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Beach Walk Grand 2 By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.