Beach Walk Residences 1 construction progress

The register lists Beach Walk Residences 1 in Palm Deira as complete, with a registered completion date of June 2026. Its last site inspection on record was in May 2026. The developer is Imtiaz Real Estate Investment & Development.

100%

Built, at the site inspection of 18 May 2026

Construction complete

Registered completion date
June 2026
Construction started
June 2024
First registered
July 2024
Community
Palm Deira
Units
76
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بيتش ووك ريزيدنسز 1
Project number
3162
Site inspections
7

Schedule

The register lists Beach Walk Residences 1 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 May 2026

100%+6.1 pts

  • Beach Walk Residences 1 construction site, inspection photo 1, 18 May 2026
  • Beach Walk Residences 1 construction site, inspection photo 2, 18 May 2026
  • Beach Walk Residences 1 construction site, inspection photo 3, 18 May 2026
  • Beach Walk Residences 1 construction site, inspection photo 4, 18 May 2026

20 January 2026

94%+15 pts

  • Beach Walk Residences 1 construction site, inspection photo 1, 20 January 2026
  • Beach Walk Residences 1 construction site, inspection photo 2, 20 January 2026
  • Beach Walk Residences 1 construction site, inspection photo 3, 20 January 2026
  • Beach Walk Residences 1 construction site, inspection photo 4, 20 January 2026

31 October 2025

79%+21 pts

  • Beach Walk Residences 1 construction site, inspection photo 1, 31 October 2025
  • Beach Walk Residences 1 construction site, inspection photo 2, 31 October 2025
  • Beach Walk Residences 1 construction site, inspection photo 3, 31 October 2025
  • Beach Walk Residences 1 construction site, inspection photo 4, 31 October 2025

24 June 2025

58%+15 pts

  • Beach Walk Residences 1 construction site, inspection photo 1, 24 June 2025
  • Beach Walk Residences 1 construction site, inspection photo 2, 24 June 2025
  • Beach Walk Residences 1 construction site, inspection photo 3, 24 June 2025
  • Beach Walk Residences 1 construction site, inspection photo 4, 24 June 2025

3 April 2025

43%+20 pts

  • Beach Walk Residences 1 construction site, inspection photo 1, 3 April 2025
  • Beach Walk Residences 1 construction site, inspection photo 2, 3 April 2025
  • Beach Walk Residences 1 construction site, inspection photo 3, 3 April 2025
  • Beach Walk Residences 1 construction site, inspection photo 4, 3 April 2025

13 December 2024

23%+23 pts

  • Beach Walk Residences 1 construction site, inspection photo 1, 13 December 2024
  • Beach Walk Residences 1 construction site, inspection photo 2, 13 December 2024
  • Beach Walk Residences 1 construction site, inspection photo 3, 13 December 2024
  • Beach Walk Residences 1 construction site, inspection photo 4, 13 December 2024

2 July 2024

0%

  • Beach Walk Residences 1 construction site, inspection photo 1, 2 July 2024
  • Beach Walk Residences 1 construction site, inspection photo 2, 2 July 2024

All 61 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Imtiaz Real Estate Investment & Development has 11 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Beach Walk Residences 1?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Beach Walk Residences 1 handover date?
Construction of Beach Walk Residences 1 is recorded as complete, with a registered completion date of June 2026. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Beach Walk Residences 1?
Beach Walk Residences 1 was 100% built at the site inspection on 18 May 2026. The site has been inspected 7 times since July 2024. The Land Department took 61 site photos at its inspections.
Is Beach Walk Residences 1 delayed?
The register lists construction as complete.
Who is building Beach Walk Residences 1?
The registered developer is Imtiaz Real Estate Investment & Development. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Beach Walk Residences 1?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.