Woodland Crest construction progress
The registered completion date for Woodland Crest in Meydan Racecourse Community is June 2027. At the last site inspection, in September 2026, it was 1.4% built. The developer is A M I S Real Estate Development.
1.4%
Built, at the site inspection of 2 September 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- June 2057
- Construction started
- July 2025
- First registered
- March 2025
- Developer
- A M I S Real Estate Development
- Community
- Meydan Racecourse Community
- Units
- 52
- Escrow bank
- United Bank Limited
- Name in Arabic
- ودلاند كريست
- Project number
- 3547
- Site inspections
- 3
Schedule
Between March 2026 and September 2026 the site added about 0.3 points a month. At that rate it would finish around June 2057, more than three months after its registered date of June 2027.
Site inspections
2 September 2026
1.4%+1.4 pts
31 March 2026
0%+0.0 pts
25 February 2025
0%
Context
Meydan Racecourse Community has 9 projects under construction, 31% built on average.
A M I S Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Woodland Crest?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Woodland Crest handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2057. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Woodland Crest?
- Woodland Crest was 1.4% built at the site inspection on 2 September 2026. The site has been inspected 3 times since February 2025. The Land Department took 9 site photos at its inspections.
- Is Woodland Crest delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Woodland Crest?
- The registered developer is A M I S Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Woodland Crest?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Woodland ResidencesAlso by A M I S Real Estate Development. 75%, Due April 2026, passed.
- Woodland TerracesAlso by A M I S Real Estate Development. 10%, Due March 2027.
- Royal ManorNearby in Meydan Racecourse Community. 78%, Due December 2018, passed.
- Tonino Lamborghini ResidencesNearby in Meydan Racecourse Community. 60%, Due December 2026.
- Emerge ResidencesNearby in Meydan Racecourse Community. 21%, Due November 2027.
- Mews MansionsNearby in Meydan Racecourse Community. 56%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)