Woodland Crest construction progress

The registered completion date for Woodland Crest in Meydan Racecourse Community is June 2027. At the last site inspection, in September 2026, it was 1.4% built. The developer is A M I S Real Estate Development.

1.4%

Built, at the site inspection of 2 September 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
June 2057
Construction started
July 2025
First registered
March 2025
Units
52
Escrow bank
United Bank Limited
Name in Arabic
ودلاند كريست
Project number
3547
Site inspections
3

Schedule

Between March 2026 and September 2026 the site added about 0.3 points a month. At that rate it would finish around June 2057, more than three months after its registered date of June 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 September 2026

1.4%+1.4 pts

  • Woodland Crest construction site, inspection photo 1, 2 September 2026
  • Woodland Crest construction site, inspection photo 2, 2 September 2026
  • Woodland Crest construction site, inspection photo 3, 2 September 2026
  • Woodland Crest construction site, inspection photo 4, 2 September 2026

31 March 2026

0%+0.0 pts

  • Woodland Crest construction site, inspection photo 1, 31 March 2026
  • Woodland Crest construction site, inspection photo 2, 31 March 2026
  • Woodland Crest construction site, inspection photo 3, 31 March 2026

25 February 2025

0%

  • Woodland Crest construction site, inspection photo 1, 25 February 2025
  • Woodland Crest construction site, inspection photo 2, 25 February 2025

All 9 site photos, by inspection date

Context

Meydan Racecourse Community has 9 projects under construction, 31% built on average.

A M I S Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Woodland Crest?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Woodland Crest handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2057. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Woodland Crest?
Woodland Crest was 1.4% built at the site inspection on 2 September 2026. The site has been inspected 3 times since February 2025. The Land Department took 9 site photos at its inspections.
Is Woodland Crest delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Woodland Crest?
The registered developer is A M I S Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Woodland Crest?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.