Woodland Terraces construction progress
The registered completion date for Woodland Terraces in Mohammed Bin Rashid Al Maktoum District 11 is March 2027. At the last site inspection, in September 2026, it was 10% built. The developer is A M I S Real Estate Development.
10%
Built, at the site inspection of 2 September 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- January 2035
- Construction started
- February 2025
- First registered
- January 2025
- Developer
- A M I S Real Estate Development
- Units
- 78
- Escrow bank
- United Bank Limited
- Name in Arabic
- ودلاند تراسيز
- Project number
- 3457
- Site inspections
- 4
Schedule
Between October 2025 and September 2026 the site added about 0.9 points a month. At that rate it would finish around January 2035, more than three months after its registered date of March 2027.
Site inspections
2 September 2026
10%+6.1 pts
26 March 2026
4.3%+3.2 pts
22 October 2025
1.1%+1.1 pts
26 December 2024
0%
Context
Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.
A M I S Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Woodland Terraces?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Woodland Terraces handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Woodland Terraces?
- Woodland Terraces was 10% built at the site inspection on 2 September 2026. The site has been inspected 4 times since December 2024. The Land Department took 13 site photos at its inspections.
- Is Woodland Terraces delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Woodland Terraces?
- The registered developer is A M I S Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Woodland Terraces?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The Woodland ResidencesAlso by A M I S Real Estate Development. 75%, Due April 2026, passed.
- Woodland CrestAlso by A M I S Real Estate Development. 1.4%, Due June 2027.
- The Waterside Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 45%, Due June 2026, passed.
- The Lakeview Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 20%, Due August 2026, passed.
- The Beachfront Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 47%, Due August 2026, passed.
- The Lakeshore Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 1.4%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)