Tonino Lamborghini Residences construction photos

92 photos from 13 site inspections, newest first. The percentage is how much of Tonino Lamborghini Residences was built on the day of each visit.

21 September 202660% built

10 September 202654% built

24 March 202652% built

30 October 202551% built

18 June 202550% built

30 January 202540% built

24 December 202434% built

7 June 202427% built

17 August 202026% built

17 April 201926% built

30 January 201920% built

12 July 201813% built

27 March 20181.2% built

Back to Tonino Lamborghini Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.