The Oasis - Lavita construction progress

The registered completion date for The Oasis - Lavita in Me'aisem Second is January 2029. At the last site inspection, in June 2026, it was 20% built. The developer is Emaar Properties.

20%

Built, at the site inspection of 2 June 2026

Running behind its date

Registered completion date
January 2029
Finish at recent pace
August 2029
Construction started
October 2024
First registered
September 2024
Units
49
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ذا اويسيس - لافيتا
Project number
3266
Site inspections
5

Schedule

Between September 2025 and June 2026 the site added about 2.1 points a month. At that rate it would finish around August 2029, more than three months after its registered date of January 2029.

0%25%50%75%100%20252026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 June 2026

20%+10 pts

  • The Oasis - Lavita construction site, inspection photo 1, 2 June 2026
  • The Oasis - Lavita construction site, inspection photo 2, 2 June 2026
  • The Oasis - Lavita construction site, inspection photo 3, 2 June 2026
  • The Oasis - Lavita construction site, inspection photo 4, 2 June 2026

5 January 2026

10%+7.9 pts

  • The Oasis - Lavita construction site, inspection photo 1, 5 January 2026
  • The Oasis - Lavita construction site, inspection photo 2, 5 January 2026
  • The Oasis - Lavita construction site, inspection photo 3, 5 January 2026
  • The Oasis - Lavita construction site, inspection photo 4, 5 January 2026

8 September 2025

2.1%+1.5 pts

  • The Oasis - Lavita construction site, inspection photo 1, 8 September 2025
  • The Oasis - Lavita construction site, inspection photo 2, 8 September 2025
  • The Oasis - Lavita construction site, inspection photo 3, 8 September 2025
  • The Oasis - Lavita construction site, inspection photo 4, 8 September 2025

13 March 2025

0.7%+0.7 pts

  • The Oasis - Lavita construction site, inspection photo 1, 13 March 2025
  • The Oasis - Lavita construction site, inspection photo 2, 13 March 2025
  • The Oasis - Lavita construction site, inspection photo 3, 13 March 2025
  • The Oasis - Lavita construction site, inspection photo 4, 13 March 2025

29 August 2024

0%

  • The Oasis - Lavita construction site, inspection photo 1, 29 August 2024
  • The Oasis - Lavita construction site, inspection photo 2, 29 August 2024

All 29 site photos, by inspection date

Context

Me'aisem Second has 7 projects under construction, 45% built on average.

Emaar Properties has 7 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Oasis - Lavita?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Oasis - Lavita handover date?
The registered completion date is January 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Oasis - Lavita?
The Oasis - Lavita was 20% built at the site inspection on 2 June 2026. The site has been inspected 5 times since August 2024. The Land Department took 29 site photos at its inspections.
Is The Oasis - Lavita delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2029.
Who is building The Oasis - Lavita?
The registered developer is Emaar Properties. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for The Oasis - Lavita?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.