The Oasis - Lavita construction progress
The registered completion date for The Oasis - Lavita in Me'aisem Second is January 2029. At the last site inspection, in June 2026, it was 20% built. The developer is Emaar Properties.
20%
Built, at the site inspection of 2 June 2026
Running behind its date
- Registered completion date
- January 2029
- Finish at recent pace
- August 2029
- Construction started
- October 2024
- First registered
- September 2024
- Developer
- Emaar Properties
- Community
- Me'aisem Second
- Units
- 49
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ذا اويسيس - لافيتا
- Project number
- 3266
- Site inspections
- 5
Schedule
Between September 2025 and June 2026 the site added about 2.1 points a month. At that rate it would finish around August 2029, more than three months after its registered date of January 2029.
Site inspections
2 June 2026
20%+10 pts
5 January 2026
10%+7.9 pts
8 September 2025
2.1%+1.5 pts
13 March 2025
0.7%+0.7 pts
29 August 2024
0%
Context
Me'aisem Second has 7 projects under construction, 45% built on average.
Emaar Properties has 7 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Oasis - Lavita?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Oasis - Lavita handover date?
- The registered completion date is January 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Oasis - Lavita?
- The Oasis - Lavita was 20% built at the site inspection on 2 June 2026. The site has been inspected 5 times since August 2024. The Land Department took 29 site photos at its inspections.
- Is The Oasis - Lavita delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2029.
- Who is building The Oasis - Lavita?
- The registered developer is Emaar Properties. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for The Oasis - Lavita?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Marina ShoresAlso by Emaar Properties. 87%, Due December 2026.
- The Oasis - PalmieraAlso by Emaar Properties. 82%.
- The Oasis - MirageAlso by Emaar Properties. 47%.
- The Oasis - Palmiera 2Also by Emaar Properties. 77%.
- The Oasis - Address Villas - TierraNearby in Me'aisem Second. 6.8%, Due June 2029.
- The Oasis - Palace Villas - OstraNearby in Me'aisem Second. 6.5%, Due September 2029.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)