The Haven construction progress

The register lists The Haven in Majan as complete, with a registered completion date of July 2025. Its last site inspection on record was in July 2025. The developer is Meraki Real Estate Development.

100%

Built, at the site inspection of 12 July 2025

Construction complete

Registered completion date
July 2025
Construction started
March 2023
First registered
August 2023
Community
Majan
Units
326
Escrow bank
Dubai Islamic Bank
Name in Arabic
ذا هيفين
Project number
2194
Site inspections
7

Schedule

The register lists The Haven as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 July 2025

100%+20 pts

  • The Haven construction site, inspection photo 1, 12 July 2025
  • The Haven construction site, inspection photo 2, 12 July 2025
  • The Haven construction site, inspection photo 3, 12 July 2025
  • The Haven construction site, inspection photo 4, 12 July 2025

28 January 2025

80%+20 pts

  • The Haven construction site, inspection photo 1, 28 January 2025
  • The Haven construction site, inspection photo 2, 28 January 2025
  • The Haven construction site, inspection photo 3, 28 January 2025
  • The Haven construction site, inspection photo 4, 28 January 2025

16 October 2024

60%+9.9 pts

  • The Haven construction site, inspection photo 1, 16 October 2024
  • The Haven construction site, inspection photo 2, 16 October 2024
  • The Haven construction site, inspection photo 3, 16 October 2024
  • The Haven construction site, inspection photo 4, 16 October 2024

28 June 2024

50%+20 pts

  • The Haven construction site, inspection photo 1, 28 June 2024
  • The Haven construction site, inspection photo 2, 28 June 2024
  • The Haven construction site, inspection photo 3, 28 June 2024
  • The Haven construction site, inspection photo 4, 28 June 2024

12 March 2024

31%+10 pts

  • The Haven construction site, inspection photo 1, 12 March 2024
  • The Haven construction site, inspection photo 2, 12 March 2024
  • The Haven construction site, inspection photo 3, 12 March 2024
  • The Haven construction site, inspection photo 4, 12 March 2024

2 November 2023

20%+11 pts

  • The Haven construction site, inspection photo 1, 2 November 2023
  • The Haven construction site, inspection photo 2, 2 November 2023
  • The Haven construction site, inspection photo 3, 2 November 2023
  • The Haven construction site, inspection photo 4, 2 November 2023

10 July 2023

8.9%

  • The Haven construction site, inspection photo 1, 10 July 2023
  • The Haven construction site, inspection photo 2, 10 July 2023
  • The Haven construction site, inspection photo 3, 10 July 2023
  • The Haven construction site, inspection photo 4, 10 July 2023

All 60 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Meraki Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Haven?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Haven handover date?
Construction of The Haven is recorded as complete, with a registered completion date of July 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Haven?
The Haven was 100% built at the site inspection on 12 July 2025. The site has been inspected 7 times since July 2023. The Land Department took 60 site photos at its inspections.
Is The Haven delayed?
The register lists construction as complete.
Who is building The Haven?
The registered developer is Meraki Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for The Haven?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.