Al Warsan Star construction progress

The registered completion date for Al Warsan Star in Warsan First Development is February 2027. At the last site inspection, in June 2026, it was 7.5% built. The developer is Rose Homes Investment.

7.5%

Built, at the site inspection of 18 June 2026

Running behind its date

Registered completion date
February 2027
Finish at recent pace
June 2035
Construction started
October 2025
First registered
December 2025
Developer
Rose Homes Investment
Units
48
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
نجمة ورسان
Project number
3674
Site inspections
2

Schedule

Between September 2025 and June 2026 the site added about 0.9 points a month. At that rate it would finish around June 2035, more than three months after its registered date of February 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 June 2026

7.5%+7.5 pts

  • Al Warsan Star construction site, inspection photo 1, 18 June 2026
  • Al Warsan Star construction site, inspection photo 2, 18 June 2026
  • Al Warsan Star construction site, inspection photo 3, 18 June 2026
  • Al Warsan Star construction site, inspection photo 4, 18 June 2026

26 September 2025

0%

  • Al Warsan Star construction site, inspection photo 1, 26 September 2025
  • Al Warsan Star construction site, inspection photo 2, 26 September 2025

All 7 site photos, by inspection date

Context

Warsan First Development has 3 projects under construction, 2.6% built on average.

Rose Homes Investment has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Al Warsan Star?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Al Warsan Star handover date?
The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Al Warsan Star?
Al Warsan Star was 7.5% built at the site inspection on 18 June 2026. The site has been inspected 2 times since September 2025. The Land Department took 7 site photos at its inspections.
Is Al Warsan Star delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Al Warsan Star?
The registered developer is Rose Homes Investment. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Al Warsan Star?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.