Al Warsan Star construction progress

Al Warsan Star in Warsan First Development is 7.5% built at the Land Department inspection of June 2026. Developer Rose Homes Investment. Completion registered for February 2027.

7.5%

Built, at the Land Department site inspection of 18 June 2026

Running behind its date

Completion date (Land Department)
February 2027
Finish at recent pace
June 2035
Construction started
October 2025
Registered with the Land Department
December 2025
Developer
Rose Homes Investment
Units
48
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
نجمة ورسان
Land Department project number
3674
Land Department site inspections
2

Schedule

Between September 2025 and June 2026 the site added about 0.9 points a month. At that rate it would finish around June 2035, more than three months after the February 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 June 2026

7.5%+7.5 pts

  • Al Warsan Star construction site, Land Department inspection photo 1, 18 June 2026
  • Al Warsan Star construction site, Land Department inspection photo 2, 18 June 2026
  • Al Warsan Star construction site, Land Department inspection photo 3, 18 June 2026
  • Al Warsan Star construction site, Land Department inspection photo 4, 18 June 2026

26 September 2025

0%

  • Al Warsan Star construction site, Land Department inspection photo 1, 26 September 2025
  • Al Warsan Star construction site, Land Department inspection photo 2, 26 September 2025

All 7 site photos, by inspection date

Context

Warsan First Development has 3 projects under construction, 2.6% built on average.

Rose Homes Investment has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Al Warsan Star?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Al Warsan Star be completed?
The completion date registered with the Dubai Land Department is February 2027. At the pace of its recent inspections the site would reach 100% around June 2035. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Al Warsan Star is built?
7.5%, measured at the Land Department site inspection on 18 June 2026. The Land Department engineers have inspected the site 2 times since September 2025.
Is Al Warsan Star delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Al Warsan Star?
The registered developer is Rose Homes Investment. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Al Warsan Star?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.