Sherena Residence 2 construction photos
59 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Sherena Residence 2 was built on the day of each visit.
22 April 202682% built
26 December 202576% built
15 February 202451% built
17 August 202347% built
6 February 202339% built
2 March 202127% built
5 May 201922% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.