Belmont Residences construction progress

The register lists Belmont Residences in Jumeirah Village Triangle as complete. Its last site inspection on record was in August 2026. The developer is Ellington Properties Development.

100%

Built, at the site inspection of 20 August 2026

Construction complete

Construction started
April 2023
First registered
July 2023
Units
69
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بلمونت ريزيدنسز
Project number
2639
Site inspections
8

Schedule

The register lists Belmont Residences as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

20 August 2026

100%+10.0 pts

  • Belmont Residences construction site, inspection photo 1, 20 August 2026
  • Belmont Residences construction site, inspection photo 2, 20 August 2026
  • Belmont Residences construction site, inspection photo 3, 20 August 2026
  • Belmont Residences construction site, inspection photo 4, 20 August 2026

26 March 2026

90%+13 pts

  • Belmont Residences construction site, inspection photo 1, 26 March 2026
  • Belmont Residences construction site, inspection photo 2, 26 March 2026
  • Belmont Residences construction site, inspection photo 3, 26 March 2026
  • Belmont Residences construction site, inspection photo 4, 26 March 2026

11 December 2025

77%+14 pts

  • Belmont Residences construction site, inspection photo 1, 11 December 2025
  • Belmont Residences construction site, inspection photo 2, 11 December 2025
  • Belmont Residences construction site, inspection photo 3, 11 December 2025
  • Belmont Residences construction site, inspection photo 4, 11 December 2025

4 September 2025

63%+21 pts

  • Belmont Residences construction site, inspection photo 1, 4 September 2025
  • Belmont Residences construction site, inspection photo 2, 4 September 2025
  • Belmont Residences construction site, inspection photo 3, 4 September 2025
  • Belmont Residences construction site, inspection photo 4, 4 September 2025

10 April 2025

43%+20 pts

  • Belmont Residences construction site, inspection photo 1, 10 April 2025
  • Belmont Residences construction site, inspection photo 2, 10 April 2025
  • Belmont Residences construction site, inspection photo 3, 10 April 2025
  • Belmont Residences construction site, inspection photo 4, 10 April 2025

20 November 2024

22%+20 pts

  • Belmont Residences construction site, inspection photo 1, 20 November 2024
  • Belmont Residences construction site, inspection photo 2, 20 November 2024
  • Belmont Residences construction site, inspection photo 3, 20 November 2024
  • Belmont Residences construction site, inspection photo 4, 20 November 2024

4 April 2024

2.5%+2.5 pts

  • Belmont Residences construction site, inspection photo 1, 4 April 2024
  • Belmont Residences construction site, inspection photo 2, 4 April 2024
  • Belmont Residences construction site, inspection photo 3, 4 April 2024
  • Belmont Residences construction site, inspection photo 4, 4 April 2024

12 April 2023

0%

  • Belmont Residences construction site, inspection photo 1, 12 April 2023
  • Belmont Residences construction site, inspection photo 2, 12 April 2023

All 58 site photos, by inspection date

Context

Jumeirah Village Triangle has 29 projects under construction, 27% built on average.

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in Belmont Residences?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Belmont Residences handover date?
Construction of Belmont Residences is recorded as complete. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Belmont Residences?
Belmont Residences was 100% built at the site inspection on 20 August 2026. The site has been inspected 8 times since April 2023. The Land Department took 58 site photos at its inspections.
Is Belmont Residences delayed?
The register lists construction as complete.
Who is building Belmont Residences?
The registered developer is Ellington Properties Development. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Belmont Residences?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.