Altai Tower construction progress

Altai Tower in Jumeirah Village Triangle is 98% built at the Land Department inspection of September 2026. Developer Tiger Properties. Completion registered for January 2026.

98%

Built, at the Land Department site inspection of 29 September 2026

8 months past its registered completion date

Completion date (Land Department)
January 2026
Finish at recent pace
October 2026
Construction started
June 2023
Registered with the Land Department
June 2023
Units
239
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
التاي تاور
Land Department project number
2636
Land Department site inspections
8

Schedule

Altai Tower was registered to complete in January 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 3.7 points a month. Kept at that rate, the site would reach 100% around October 2026.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

29 September 2026

98%+3.4 pts

  • Altai Tower construction site, Land Department inspection photo 1, 29 September 2026
  • Altai Tower construction site, Land Department inspection photo 2, 29 September 2026
  • Altai Tower construction site, Land Department inspection photo 3, 29 September 2026
  • Altai Tower construction site, Land Department inspection photo 4, 29 September 2026

11 August 2026

95%+13 pts

  • Altai Tower construction site, Land Department inspection photo 1, 11 August 2026
  • Altai Tower construction site, Land Department inspection photo 2, 11 August 2026
  • Altai Tower construction site, Land Department inspection photo 3, 11 August 2026
  • Altai Tower construction site, Land Department inspection photo 4, 11 August 2026

27 April 2026

82%+16 pts

  • Altai Tower construction site, Land Department inspection photo 1, 27 April 2026
  • Altai Tower construction site, Land Department inspection photo 2, 27 April 2026
  • Altai Tower construction site, Land Department inspection photo 3, 27 April 2026
  • Altai Tower construction site, Land Department inspection photo 4, 27 April 2026

29 December 2025

66%+35 pts

  • Altai Tower construction site, Land Department inspection photo 1, 29 December 2025
  • Altai Tower construction site, Land Department inspection photo 2, 29 December 2025
  • Altai Tower construction site, Land Department inspection photo 3, 29 December 2025
  • Altai Tower construction site, Land Department inspection photo 4, 29 December 2025

22 July 2025

31%+17 pts

  • Altai Tower construction site, Land Department inspection photo 1, 22 July 2025
  • Altai Tower construction site, Land Department inspection photo 2, 22 July 2025
  • Altai Tower construction site, Land Department inspection photo 3, 22 July 2025
  • Altai Tower construction site, Land Department inspection photo 4, 22 July 2025

18 February 2025

13%+13 pts

  • Altai Tower construction site, Land Department inspection photo 1, 18 February 2025
  • Altai Tower construction site, Land Department inspection photo 2, 18 February 2025
  • Altai Tower construction site, Land Department inspection photo 3, 18 February 2025
  • Altai Tower construction site, Land Department inspection photo 4, 18 February 2025

8 July 2024

0.7%+0.7 pts

  • Altai Tower construction site, Land Department inspection photo 1, 8 July 2024
  • Altai Tower construction site, Land Department inspection photo 2, 8 July 2024
  • Altai Tower construction site, Land Department inspection photo 3, 8 July 2024

25 May 2023

0%

  • Altai Tower construction site, Land Department inspection photo 1, 25 May 2023
  • Altai Tower construction site, Land Department inspection photo 2, 25 May 2023
  • Altai Tower construction site, Land Department inspection photo 3, 25 May 2023

All 70 site photos, by inspection date

Context

Jumeirah Village Triangle has 31 projects under construction, 28% built on average.

Tiger Properties has 9 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Altai Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Altai Tower be completed?
The completion date registered with the Dubai Land Department is January 2026. At the pace of its recent inspections the site would reach 100% around October 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Altai Tower is built?
98%, measured at the Land Department site inspection on 29 September 2026. The Land Department engineers have inspected the site 8 times since May 2023.
Is Altai Tower delayed?
Yes. Its registered completion date of January 2026 has passed and the Land Department still lists it as under construction.
Who is building Altai Tower?
The registered developer is Tiger Properties. It has 8 other projects under construction in Dubai.
Which bank holds the escrow account for Altai Tower?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.