Altai Tower construction progress
Altai Tower in Jumeirah Village Triangle is 98% built at the Land Department inspection of September 2026. Developer Tiger Properties. Completion registered for January 2026.
98%
Built, at the Land Department site inspection of 29 September 2026
8 months past its registered completion date
- Completion date (Land Department)
- January 2026
- Finish at recent pace
- October 2026
- Construction started
- June 2023
- Registered with the Land Department
- June 2023
- Developer
- Tiger Properties
- Community
- Jumeirah Village Triangle
- Units
- 239
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- التاي تاور
- Land Department project number
- 2636
- Land Department site inspections
- 8
Schedule
Altai Tower was registered to complete in January 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 3.7 points a month. Kept at that rate, the site would reach 100% around October 2026.
Site inspections
29 September 2026
98%+3.4 pts
11 August 2026
95%+13 pts
27 April 2026
82%+16 pts
29 December 2025
66%+35 pts
22 July 2025
31%+17 pts
18 February 2025
13%+13 pts
8 July 2024
0.7%+0.7 pts
25 May 2023
0%
Context
Jumeirah Village Triangle has 31 projects under construction, 28% built on average.
Tiger Properties has 9 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Altai Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Altai Tower be completed?
- The completion date registered with the Dubai Land Department is January 2026. At the pace of its recent inspections the site would reach 100% around October 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Altai Tower is built?
- 98%, measured at the Land Department site inspection on 29 September 2026. The Land Department engineers have inspected the site 8 times since May 2023.
- Is Altai Tower delayed?
- Yes. Its registered completion date of January 2026 has passed and the Land Department still lists it as under construction.
- Who is building Altai Tower?
- The registered developer is Tiger Properties. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Altai Tower?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Tiger Sky TowerAlso by Tiger Properties. 10%.
- Volga TowerAlso by Tiger Properties. 51%.
- Red SquareAlso by Tiger Properties. 27%.
- Jade TowerAlso by Tiger Properties. 11%.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Santorini Residences By LoutrakiNearby in Jumeirah Village Triangle. 43%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.