The East Crest By Meteora construction progress

The register lists The East Crest By Meteora in Jumeirah Village Circle as complete, with a registered completion date of March 2025. Its last site inspection on record was in November 2025. The developer is Meteora Real Estate Development.

100%

Built, at the site inspection of 18 November 2025

Construction complete

Registered completion date
March 2025
Construction started
March 2023
First registered
April 2023
Units
121
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ذا ايست كريست بواسطة ميتيورا
Project number
2558
Site inspections
5

Schedule

The register lists The East Crest By Meteora as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 November 2025

100%+14 pts

  • The East Crest By Meteora construction site, inspection photo 1, 18 November 2025
  • The East Crest By Meteora construction site, inspection photo 2, 18 November 2025
  • The East Crest By Meteora construction site, inspection photo 3, 18 November 2025
  • The East Crest By Meteora construction site, inspection photo 4, 18 November 2025

27 August 2024

86%+16 pts

  • The East Crest By Meteora construction site, inspection photo 1, 27 August 2024
  • The East Crest By Meteora construction site, inspection photo 2, 27 August 2024
  • The East Crest By Meteora construction site, inspection photo 3, 27 August 2024

8 May 2024

71%+18 pts

  • The East Crest By Meteora construction site, inspection photo 1, 8 May 2024
  • The East Crest By Meteora construction site, inspection photo 2, 8 May 2024
  • The East Crest By Meteora construction site, inspection photo 3, 8 May 2024
  • The East Crest By Meteora construction site, inspection photo 4, 8 May 2024

15 November 2023

52%+25 pts

  • The East Crest By Meteora construction site, inspection photo 1, 15 November 2023
  • The East Crest By Meteora construction site, inspection photo 2, 15 November 2023
  • The East Crest By Meteora construction site, inspection photo 3, 15 November 2023
  • The East Crest By Meteora construction site, inspection photo 4, 15 November 2023

23 January 2023

27%

  • The East Crest By Meteora construction site, inspection photo 1, 23 January 2023
  • The East Crest By Meteora construction site, inspection photo 2, 23 January 2023
  • The East Crest By Meteora construction site, inspection photo 3, 23 January 2023
  • The East Crest By Meteora construction site, inspection photo 4, 23 January 2023

All 38 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Meteora Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in The East Crest By Meteora?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The East Crest By Meteora handover date?
Construction of The East Crest By Meteora is recorded as complete, with a registered completion date of March 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The East Crest By Meteora?
The East Crest By Meteora was 100% built at the site inspection on 18 November 2025. The site has been inspected 5 times since January 2023. The Land Department took 38 site photos at its inspections.
Is The East Crest By Meteora delayed?
The register lists construction as complete.
Who is building The East Crest By Meteora?
The registered developer is Meteora Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for The East Crest By Meteora?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.