Park Boulevard By Meteora construction progress

The registered completion date for Park Boulevard By Meteora in Jumeirah Village Circle is July 2027. At the last site inspection, in March 2026, it was 30% built. The developer is Meteora Real Estate Development.

30%

Built, at the site inspection of 10 March 2026

Running behind its date

Registered completion date
July 2027
Finish at recent pace
August 2031
Construction started
December 2023
First registered
June 2024
Units
143
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
بارك بوليفارد باى ميتيورا
Project number
3045
Site inspections
3

Schedule

Between March 2025 and March 2026 the site added about 1.1 points a month. At that rate it would finish around August 2031, more than three months after its registered date of July 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 March 2026

30%+12 pts

  • Park Boulevard By Meteora construction site, inspection photo 1, 10 March 2026
  • Park Boulevard By Meteora construction site, inspection photo 2, 10 March 2026
  • Park Boulevard By Meteora construction site, inspection photo 3, 10 March 2026
  • Park Boulevard By Meteora construction site, inspection photo 4, 10 March 2026

25 March 2025

18%+10 pts

  • Park Boulevard By Meteora construction site, inspection photo 1, 25 March 2025
  • Park Boulevard By Meteora construction site, inspection photo 2, 25 March 2025
  • Park Boulevard By Meteora construction site, inspection photo 3, 25 March 2025
  • Park Boulevard By Meteora construction site, inspection photo 4, 25 March 2025

2 May 2024

7.5%

  • Park Boulevard By Meteora construction site, inspection photo 1, 2 May 2024
  • Park Boulevard By Meteora construction site, inspection photo 2, 2 May 2024
  • Park Boulevard By Meteora construction site, inspection photo 3, 2 May 2024
  • Park Boulevard By Meteora construction site, inspection photo 4, 2 May 2024

All 15 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Meteora Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Park Boulevard By Meteora?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Park Boulevard By Meteora handover date?
The registered completion date is July 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Park Boulevard By Meteora?
Park Boulevard By Meteora was 30% built at the site inspection on 10 March 2026. The site has been inspected 3 times since May 2024. The Land Department took 15 site photos at its inspections.
Is Park Boulevard By Meteora delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
Who is building Park Boulevard By Meteora?
The registered developer is Meteora Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Park Boulevard By Meteora?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.