The East Crest By Meteora construction photos

38 photos from 5 site inspections, newest first. The percentage is how much of The East Crest By Meteora was built on the day of each visit.

18 November 2025100% built

27 August 202486% built

8 May 202471% built

15 November 202352% built

23 January 202327% built

Back to The East Crest By Meteora construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.