Squarex Residence construction progress

Squarex Residence in Jumeirah Village Circle is 58% built at the Land Department inspection of September 2026. Developer Tasmeer Indigo Real Estate Development.

58%

Built, at the Land Department site inspection of 1 September 2026

Finish at recent pace
September 2027
Construction started
April 2024
Registered with the Land Department
February 2024
Developer
Tasmeer Indigo Real Estate Development
Units
175
Escrow bank
United Bank Limited
Name in Arabic
سكوير اكس ريزيدنس
Land Department project number
2919
Land Department site inspections
7

Schedule

Since October 2025 Squarex Residence has added about 3.4 points a month. At that rate the site reaches 100% around September 2027. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%20252026
Progress at each Land Department site inspection

Site inspections

1 September 2026

58%+1.8 pts

  • Squarex Residence construction site, Land Department inspection photo 1, 1 September 2026
  • Squarex Residence construction site, Land Department inspection photo 2, 1 September 2026
  • Squarex Residence construction site, Land Department inspection photo 3, 1 September 2026
  • Squarex Residence construction site, Land Department inspection photo 4, 1 September 2026

8 July 2026

56%+16 pts

  • Squarex Residence construction site, Land Department inspection photo 1, 8 July 2026
  • Squarex Residence construction site, Land Department inspection photo 2, 8 July 2026
  • Squarex Residence construction site, Land Department inspection photo 3, 8 July 2026
  • Squarex Residence construction site, Land Department inspection photo 4, 8 July 2026

13 February 2026

40%+17 pts

  • Squarex Residence construction site, Land Department inspection photo 1, 13 February 2026
  • Squarex Residence construction site, Land Department inspection photo 2, 13 February 2026
  • Squarex Residence construction site, Land Department inspection photo 3, 13 February 2026
  • Squarex Residence construction site, Land Department inspection photo 4, 13 February 2026

22 October 2025

23%+6.6 pts

  • Squarex Residence construction site, Land Department inspection photo 1, 22 October 2025
  • Squarex Residence construction site, Land Department inspection photo 2, 22 October 2025
  • Squarex Residence construction site, Land Department inspection photo 3, 22 October 2025
  • Squarex Residence construction site, Land Department inspection photo 4, 22 October 2025

19 August 2025

16%+11 pts

  • Squarex Residence construction site, Land Department inspection photo 1, 19 August 2025
  • Squarex Residence construction site, Land Department inspection photo 2, 19 August 2025
  • Squarex Residence construction site, Land Department inspection photo 3, 19 August 2025
  • Squarex Residence construction site, Land Department inspection photo 4, 19 August 2025

3 January 2025

5.5%+5.5 pts

  • Squarex Residence construction site, Land Department inspection photo 1, 3 January 2025
  • Squarex Residence construction site, Land Department inspection photo 2, 3 January 2025
  • Squarex Residence construction site, Land Department inspection photo 3, 3 January 2025
  • Squarex Residence construction site, Land Department inspection photo 4, 3 January 2025

18 January 2024

0%

  • Squarex Residence construction site, Land Department inspection photo 1, 18 January 2024
  • Squarex Residence construction site, Land Department inspection photo 2, 18 January 2024
  • Squarex Residence construction site, Land Department inspection photo 3, 18 January 2024

All 45 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average. Squarex Residence is ahead of that average.

Tasmeer Indigo Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Squarex Residence?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Squarex Residence be completed?
The Land Department has no completion date on record for Squarex Residence yet. It appears once the developer registers the construction timeline.
How much of Squarex Residence is built?
58%, measured at the Land Department site inspection on 1 September 2026. The Land Department engineers have inspected the site 7 times since January 2024.
Who is building Squarex Residence?
The registered developer is Tasmeer Indigo Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Squarex Residence?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.