Squarex One construction progress
The registered completion date for Squarex One in Jumeirah Village Circle is June 2028. At the last site inspection, in December 2025, it was 0% built. The developer is Tasmeer Indigo Real Estate Development.
0%
Built, at the site inspection of 24 December 2025
Running behind its date
- Registered completion date
- June 2028
- Construction started
- December 2025
- First registered
- January 2026
- Developer
- Tasmeer Indigo Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 207
- Escrow bank
- United Bank Limited
- Name in Arabic
- سكويراكس ون
- Project number
- 3371
- Site inspections
- 2
Schedule
Site inspections
24 December 2025
0%
11 November 2024
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Tasmeer Indigo Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Squarex One?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Squarex One handover date?
- The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Squarex One?
- Squarex One was 0% built at the site inspection on 24 December 2025. The site has been inspected 2 times since November 2024. The Land Department took 5 site photos at its inspections.
- Is Squarex One delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building Squarex One?
- The registered developer is Tasmeer Indigo Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Squarex One?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Squarex ResidenceAlso by Tasmeer Indigo Real Estate Development. 58%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




