Squarex Residence construction photos

45 photos from 7 site inspections, newest first. The percentage is how much of Squarex Residence was built on the day of each visit.

1 September 202658% built

8 July 202656% built

13 February 202640% built

22 October 202523% built

19 August 202516% built

3 January 20255.5% built

18 January 20240% built

Back to Squarex Residence construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.