Serenity Lakes 5 construction progress

The register lists Serenity Lakes 5 in Jumeirah Village Circle as complete, with a registered completion date of September 2022. Its last site inspection on record was in February 2024. The developer is Gulf Land Property Developers.

100%

Built, at the site inspection of 14 February 2024

Construction complete

Registered completion date
September 2022
Construction started
June 2014
First registered
August 2014
Units
305
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بحيرات الصفاء 5
Project number
1554
Site inspections
13

Schedule

The register lists Serenity Lakes 5 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20152017201920212023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 February 2024

100%+14 pts

  • Serenity Lakes 5 construction site, inspection photo 1, 14 February 2024
  • Serenity Lakes 5 construction site, inspection photo 2, 14 February 2024
  • Serenity Lakes 5 construction site, inspection photo 3, 14 February 2024
  • Serenity Lakes 5 construction site, inspection photo 4, 14 February 2024

29 December 2022

86%+4.3 pts

  • Serenity Lakes 5 construction site, inspection photo 1, 29 December 2022
  • Serenity Lakes 5 construction site, inspection photo 2, 29 December 2022
  • Serenity Lakes 5 construction site, inspection photo 3, 29 December 2022
  • Serenity Lakes 5 construction site, inspection photo 4, 29 December 2022

27 July 2022

82%+1.7 pts

  • Serenity Lakes 5 construction site, inspection photo 1, 27 July 2022
  • Serenity Lakes 5 construction site, inspection photo 2, 27 July 2022
  • Serenity Lakes 5 construction site, inspection photo 3, 27 July 2022
  • Serenity Lakes 5 construction site, inspection photo 4, 27 July 2022

24 March 2022

80%+9.9 pts

  • Serenity Lakes 5 construction site, inspection photo 1, 24 March 2022
  • Serenity Lakes 5 construction site, inspection photo 2, 24 March 2022
  • Serenity Lakes 5 construction site, inspection photo 3, 24 March 2022
  • Serenity Lakes 5 construction site, inspection photo 4, 24 March 2022

6 December 2021

70%+5.1 pts

  • Serenity Lakes 5 construction site, inspection photo 1, 6 December 2021
  • Serenity Lakes 5 construction site, inspection photo 2, 6 December 2021
  • Serenity Lakes 5 construction site, inspection photo 3, 6 December 2021
  • Serenity Lakes 5 construction site, inspection photo 4, 6 December 2021

6 July 2021

65%+10 pts

  • Serenity Lakes 5 construction site, inspection photo 1, 6 July 2021
  • Serenity Lakes 5 construction site, inspection photo 2, 6 July 2021
  • Serenity Lakes 5 construction site, inspection photo 3, 6 July 2021
  • Serenity Lakes 5 construction site, inspection photo 4, 6 July 2021

24 March 2021

55%+7.9 pts

  • Serenity Lakes 5 construction site, inspection photo 1, 24 March 2021
  • Serenity Lakes 5 construction site, inspection photo 2, 24 March 2021
  • Serenity Lakes 5 construction site, inspection photo 3, 24 March 2021
  • Serenity Lakes 5 construction site, inspection photo 4, 24 March 2021

29 April 2019

47%+3.4 pts

  • Serenity Lakes 5 construction site, inspection photo 1, 29 April 2019
  • Serenity Lakes 5 construction site, inspection photo 2, 29 April 2019
  • Serenity Lakes 5 construction site, inspection photo 3, 29 April 2019
  • Serenity Lakes 5 construction site, inspection photo 4, 29 April 2019

26 February 2018

44%+8.9 pts

  • Serenity Lakes 5 construction site, inspection photo 1, 26 February 2018
  • Serenity Lakes 5 construction site, inspection photo 2, 26 February 2018
  • Serenity Lakes 5 construction site, inspection photo 3, 26 February 2018
  • Serenity Lakes 5 construction site, inspection photo 4, 26 February 2018

20 September 2017

35%+16 pts

  • Serenity Lakes 5 construction site, inspection photo 1, 20 September 2017
  • Serenity Lakes 5 construction site, inspection photo 2, 20 September 2017
  • Serenity Lakes 5 construction site, inspection photo 3, 20 September 2017

All 114 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Gulf Land Property Developers has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Serenity Lakes 5?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Serenity Lakes 5 handover date?
Construction of Serenity Lakes 5 is recorded as complete, with a registered completion date of September 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Serenity Lakes 5?
Serenity Lakes 5 was 100% built at the site inspection on 14 February 2024. The site has been inspected 13 times since July 2015. The Land Department took 114 site photos at its inspections.
Is Serenity Lakes 5 delayed?
The register lists construction as complete.
Who is building Serenity Lakes 5?
The registered developer is Gulf Land Property Developers. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Serenity Lakes 5?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.