Serenity Lakes 5 construction progress
The register lists Serenity Lakes 5 in Jumeirah Village Circle as complete, with a registered completion date of September 2022. Its last site inspection on record was in February 2024. The developer is Gulf Land Property Developers.
100%
Built, at the site inspection of 14 February 2024
Construction complete
- Registered completion date
- September 2022
- Construction started
- June 2014
- First registered
- August 2014
- Developer
- Gulf Land Property Developers
- Community
- Jumeirah Village Circle
- Units
- 305
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- بحيرات الصفاء 5
- Project number
- 1554
- Site inspections
- 13
Schedule
The register lists Serenity Lakes 5 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
14 February 2024
100%+14 pts
29 December 2022
86%+4.3 pts
27 July 2022
82%+1.7 pts
24 March 2022
80%+9.9 pts
6 December 2021
70%+5.1 pts
6 July 2021
65%+10 pts
24 March 2021
55%+7.9 pts
29 April 2019
47%+3.4 pts
26 February 2018
44%+8.9 pts
20 September 2017
35%+16 pts
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Gulf Land Property Developers has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Serenity Lakes 5?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Serenity Lakes 5 handover date?
- Construction of Serenity Lakes 5 is recorded as complete, with a registered completion date of September 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Serenity Lakes 5?
- Serenity Lakes 5 was 100% built at the site inspection on 14 February 2024. The site has been inspected 13 times since July 2015. The Land Department took 114 site photos at its inspections.
- Is Serenity Lakes 5 delayed?
- The register lists construction as complete.
- Who is building Serenity Lakes 5?
- The registered developer is Gulf Land Property Developers. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Serenity Lakes 5?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Aliva GreenAlso by Gulf Land Property Developers. 52%, Due November 2025, passed.
- Tonino Lamborghini ResidencesAlso by Gulf Land Property Developers. 60%, Due December 2026.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Luxury Family ResidenceNearby in Jumeirah Village Circle. 76%, Due December 2023, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)