Skip to content

Roxana Residence construction progress

The register lists Roxana Residence in Jumeirah Village Circle as complete, with a registered completion date of July 2019. Its last site inspection on record was in July 2019. The developer is Rose Homes Investment.

100%

Built, at the site inspection of 28 July 2019

Construction complete

Registered completion date
July 2019
Construction started
November 2015
First registered
January 2017
Units
255
Escrow bank
Commercial Bank of Dubai
Name in Arabic
مجمع روكسانا السكني
Project number
1844
Site inspections
6

Schedule

The register lists Roxana Residence as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2016201720182019
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 July 2019

100%+1.5 pts

  • Roxana Residence construction site, inspection photo 1, 28 July 2019
  • Roxana Residence construction site, inspection photo 2, 28 July 2019
  • Roxana Residence construction site, inspection photo 3, 28 July 2019
  • Roxana Residence construction site, inspection photo 4, 28 July 2019

2 July 2019

98%+15 pts

  • Roxana Residence construction site, inspection photo 1, 2 July 2019
  • Roxana Residence construction site, inspection photo 2, 2 July 2019
  • Roxana Residence construction site, inspection photo 3, 2 July 2019
  • Roxana Residence construction site, inspection photo 4, 2 July 2019

25 July 2018

84%+13 pts

  • Roxana Residence construction site, inspection photo 1, 25 July 2018
  • Roxana Residence construction site, inspection photo 2, 25 July 2018
  • Roxana Residence construction site, inspection photo 3, 25 July 2018
  • Roxana Residence construction site, inspection photo 4, 25 July 2018

20 February 2018

70%+15 pts

  • Roxana Residence construction site, inspection photo 1, 20 February 2018
  • Roxana Residence construction site, inspection photo 2, 20 February 2018
  • Roxana Residence construction site, inspection photo 3, 20 February 2018
  • Roxana Residence construction site, inspection photo 4, 20 February 2018

25 September 2017

55%+21 pts

  • Roxana Residence construction site, inspection photo 1, 25 September 2017
  • Roxana Residence construction site, inspection photo 2, 25 September 2017
  • Roxana Residence construction site, inspection photo 3, 25 September 2017
  • Roxana Residence construction site, inspection photo 4, 25 September 2017

17 April 2017

34%

  • Roxana Residence construction site, inspection photo 1, 17 April 2017
  • Roxana Residence construction site, inspection photo 2, 17 April 2017
  • Roxana Residence construction site, inspection photo 3, 17 April 2017
  • Roxana Residence construction site, inspection photo 4, 17 April 2017

All 66 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Rose Homes Investment has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Roxana Residence?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Roxana Residence handover date?
Construction of Roxana Residence is recorded as complete, with a registered completion date of July 2019. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Roxana Residence?
Roxana Residence was 100% built at the site inspection on 28 July 2019. The site has been inspected 6 times since April 2017. The Land Department took 66 site photos at its inspections.
Is Roxana Residence delayed?
The register lists construction as complete.
Who is building Roxana Residence?
The registered developer is Rose Homes Investment. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Roxana Residence?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.