Ra1n Residence construction progress

The register lists Ra1n Residence in Jumeirah Village Circle as complete, with a registered completion date of February 2025. Its last site inspection on record was in March 2026. The developer is Object One Real Estate Development.

100%

Built, at the site inspection of 10 March 2026

Construction complete

Registered completion date
February 2025
Construction started
January 2023
First registered
July 2023
Units
146
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
رأ 1 ن سكن
Project number
2635
Site inspections
8

Schedule

The register lists Ra1n Residence as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 March 2026

100%+4.0 pts

  • Ra1n Residence construction site, inspection photo 1, 10 March 2026
  • Ra1n Residence construction site, inspection photo 2, 10 March 2026
  • Ra1n Residence construction site, inspection photo 3, 10 March 2026
  • Ra1n Residence construction site, inspection photo 4, 10 March 2026

24 December 2025

96%+4.4 pts

  • Ra1n Residence construction site, inspection photo 1, 24 December 2025
  • Ra1n Residence construction site, inspection photo 2, 24 December 2025
  • Ra1n Residence construction site, inspection photo 3, 24 December 2025
  • Ra1n Residence construction site, inspection photo 4, 24 December 2025

14 July 2025

92%+19 pts

  • Ra1n Residence construction site, inspection photo 1, 14 July 2025
  • Ra1n Residence construction site, inspection photo 2, 14 July 2025
  • Ra1n Residence construction site, inspection photo 3, 14 July 2025
  • Ra1n Residence construction site, inspection photo 4, 14 July 2025

30 January 2025

73%+38 pts

  • Ra1n Residence construction site, inspection photo 1, 30 January 2025
  • Ra1n Residence construction site, inspection photo 2, 30 January 2025
  • Ra1n Residence construction site, inspection photo 3, 30 January 2025
  • Ra1n Residence construction site, inspection photo 4, 30 January 2025

3 June 2024

35%+15 pts

  • Ra1n Residence construction site, inspection photo 1, 3 June 2024
  • Ra1n Residence construction site, inspection photo 2, 3 June 2024
  • Ra1n Residence construction site, inspection photo 3, 3 June 2024
  • Ra1n Residence construction site, inspection photo 4, 3 June 2024

7 December 2023

20%+10 pts

  • Ra1n Residence construction site, inspection photo 1, 7 December 2023
  • Ra1n Residence construction site, inspection photo 2, 7 December 2023
  • Ra1n Residence construction site, inspection photo 3, 7 December 2023
  • Ra1n Residence construction site, inspection photo 4, 7 December 2023

23 August 2023

10%+6.4 pts

  • Ra1n Residence construction site, inspection photo 1, 23 August 2023
  • Ra1n Residence construction site, inspection photo 2, 23 August 2023
  • Ra1n Residence construction site, inspection photo 3, 23 August 2023
  • Ra1n Residence construction site, inspection photo 4, 23 August 2023

13 April 2023

3.8%

  • Ra1n Residence construction site, inspection photo 1, 13 April 2023
  • Ra1n Residence construction site, inspection photo 2, 13 April 2023
  • Ra1n Residence construction site, inspection photo 3, 13 April 2023
  • Ra1n Residence construction site, inspection photo 4, 13 April 2023

All 62 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Object One Real Estate Development has 13 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Ra1n Residence?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Ra1n Residence handover date?
Construction of Ra1n Residence is recorded as complete, with a registered completion date of February 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Ra1n Residence?
Ra1n Residence was 100% built at the site inspection on 10 March 2026. The site has been inspected 8 times since April 2023. The Land Department took 62 site photos at its inspections.
Is Ra1n Residence delayed?
The register lists construction as complete.
Who is building Ra1n Residence?
The registered developer is Object One Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Ra1n Residence?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.