Pearl House IV By Imtiaz construction progress

The registered completion date for Pearl House IV By Imtiaz in Jumeirah Village Circle is February 2028. At the last site inspection, in October 2026, it was 18% built. The developer is Imtiaz Luxury Real Estate Development.

18%

Built, at the site inspection of 7 October 2026

Running behind its date

Registered completion date
February 2028
Finish at recent pace
December 2030
Construction started
October 2025
First registered
October 2025
Developer
Imtiaz Luxury Real Estate Development
Units
211
Escrow bank
First Abu Dhabi Bank
Name in Arabic
من امتياز Iv بيرل هاوس
Project number
4129
Site inspections
5

Schedule

Between January 2026 and October 2026 the site added about 1.6 points a month. At that rate it would finish around December 2030, more than three months after its registered date of February 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 October 2026

18%+4.7 pts

  • Pearl House IV By Imtiaz construction site, inspection photo 1, 7 October 2026
  • Pearl House IV By Imtiaz construction site, inspection photo 2, 7 October 2026
  • Pearl House IV By Imtiaz construction site, inspection photo 3, 7 October 2026
  • Pearl House IV By Imtiaz construction site, inspection photo 4, 7 October 2026

15 July 2026

13%+6.3 pts

  • Pearl House IV By Imtiaz construction site, inspection photo 1, 15 July 2026
  • Pearl House IV By Imtiaz construction site, inspection photo 2, 15 July 2026
  • Pearl House IV By Imtiaz construction site, inspection photo 3, 15 July 2026
  • Pearl House IV By Imtiaz construction site, inspection photo 4, 15 July 2026

24 April 2026

7.0%+3.4 pts

  • Pearl House IV By Imtiaz construction site, inspection photo 1, 24 April 2026
  • Pearl House IV By Imtiaz construction site, inspection photo 2, 24 April 2026
  • Pearl House IV By Imtiaz construction site, inspection photo 3, 24 April 2026
  • Pearl House IV By Imtiaz construction site, inspection photo 4, 24 April 2026

14 January 2026

3.6%+3.6 pts

  • Pearl House IV By Imtiaz construction site, inspection photo 1, 14 January 2026
  • Pearl House IV By Imtiaz construction site, inspection photo 2, 14 January 2026
  • Pearl House IV By Imtiaz construction site, inspection photo 3, 14 January 2026
  • Pearl House IV By Imtiaz construction site, inspection photo 4, 14 January 2026

29 September 2025

0%

  • Pearl House IV By Imtiaz construction site, inspection photo 1, 29 September 2025
  • Pearl House IV By Imtiaz construction site, inspection photo 2, 29 September 2025

All 24 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Imtiaz Luxury Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Pearl House IV By Imtiaz?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Pearl House IV By Imtiaz handover date?
The registered completion date is February 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Pearl House IV By Imtiaz?
Pearl House IV By Imtiaz was 18% built at the site inspection on 7 October 2026. The site has been inspected 5 times since September 2025. The Land Department took 24 site photos at its inspections.
Is Pearl House IV By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
Who is building Pearl House IV By Imtiaz?
The registered developer is Imtiaz Luxury Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Pearl House IV By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.