Seacliff By Imtiaz construction progress

Seacliff By Imtiaz is 4.7% built at the Land Department inspection of July 2026. Developer Imtiaz Luxury Real Estate Development. Completion registered for August 2028.

4.7%

Built, at the Land Department site inspection of 20 July 2026

Running behind its date

Completion date (Land Department)
August 2028
Finish at recent pace
September 2037
Construction started
February 2026
Registered with the Land Department
February 2026
Developer
Imtiaz Luxury Real Estate Development
Units
170
Escrow bank
United Bank Limited
Name in Arabic
سي كليف من امتياز
Land Department project number
4306
Land Department site inspections
3

Schedule

Between December 2025 and July 2026 the site added about 0.7 points a month. At that rate it would finish around September 2037, more than three months after the August 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

20 July 2026

4.7%+3.6 pts

  • Seacliff By Imtiaz construction site, Land Department inspection photo 1, 20 July 2026
  • Seacliff By Imtiaz construction site, Land Department inspection photo 2, 20 July 2026
  • Seacliff By Imtiaz construction site, Land Department inspection photo 3, 20 July 2026
  • Seacliff By Imtiaz construction site, Land Department inspection photo 4, 20 July 2026

24 April 2026

1.1%+1.1 pts

  • Seacliff By Imtiaz construction site, Land Department inspection photo 1, 24 April 2026
  • Seacliff By Imtiaz construction site, Land Department inspection photo 2, 24 April 2026
  • Seacliff By Imtiaz construction site, Land Department inspection photo 3, 24 April 2026
  • Seacliff By Imtiaz construction site, Land Department inspection photo 4, 24 April 2026

30 December 2025

0%

  • Seacliff By Imtiaz construction site, Land Department inspection photo 1, 30 December 2025
  • Seacliff By Imtiaz construction site, Land Department inspection photo 2, 30 December 2025
  • Seacliff By Imtiaz construction site, Land Department inspection photo 3, 30 December 2025

All 13 site photos, by inspection date

Context

Imtiaz Luxury Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Seacliff By Imtiaz?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Seacliff By Imtiaz be completed?
The completion date registered with the Dubai Land Department is August 2028. At the pace of its recent inspections the site would reach 100% around September 2037. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Seacliff By Imtiaz is built?
4.7%, measured at the Land Department site inspection on 20 July 2026. The Land Department engineers have inspected the site 3 times since December 2025.
Is Seacliff By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
Who is building Seacliff By Imtiaz?
The registered developer is Imtiaz Luxury Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Seacliff By Imtiaz?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.