Seacliff By Imtiaz construction progress
Seacliff By Imtiaz is 4.7% built at the Land Department inspection of July 2026. Developer Imtiaz Luxury Real Estate Development. Completion registered for August 2028.
4.7%
Built, at the Land Department site inspection of 20 July 2026
Running behind its date
- Completion date (Land Department)
- August 2028
- Finish at recent pace
- September 2037
- Construction started
- February 2026
- Registered with the Land Department
- February 2026
- Developer
- Imtiaz Luxury Real Estate Development
- Units
- 170
- Escrow bank
- United Bank Limited
- Name in Arabic
- سي كليف من امتياز
- Land Department project number
- 4306
- Land Department site inspections
- 3
Schedule
Between December 2025 and July 2026 the site added about 0.7 points a month. At that rate it would finish around September 2037, more than three months after the August 2028 date registered with the Land Department.
Site inspections
20 July 2026
4.7%+3.6 pts
24 April 2026
1.1%+1.1 pts
30 December 2025
0%
Context
Imtiaz Luxury Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Seacliff By Imtiaz?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Seacliff By Imtiaz be completed?
- The completion date registered with the Dubai Land Department is August 2028. At the pace of its recent inspections the site would reach 100% around September 2037. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Seacliff By Imtiaz is built?
- 4.7%, measured at the Land Department site inspection on 20 July 2026. The Land Department engineers have inspected the site 3 times since December 2025.
- Is Seacliff By Imtiaz delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
- Who is building Seacliff By Imtiaz?
- The registered developer is Imtiaz Luxury Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Seacliff By Imtiaz?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)