Pearl House IV By Imtiaz construction photos
24 photos from 5 site inspections, newest first. The percentage is how much of Pearl House IV By Imtiaz was built on the day of each visit.
7 October 202618% built
15 July 202613% built
24 April 20267.0% built
14 January 20263.6% built
29 September 20250% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.