Mak I'Sola Bella construction progress
The registered completion date for Mak I'Sola Bella in Jumeirah Village Circle is September 2027. At the last site inspection, in August 2026, it was 27% built. The developer is Mak Developers.
27%
Built, at the site inspection of 20 August 2026
Running behind its date
- Registered completion date
- September 2027
- Finish at recent pace
- January 2030
- Construction started
- September 2024
- First registered
- September 2024
- Developer
- Mak Developers
- Community
- Jumeirah Village Circle
- Units
- 207
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ماك إيسولا بيلا
- Project number
- 3096
- Site inspections
- 6
Schedule
Between October 2025 and August 2026 the site added about 1.8 points a month. At that rate it would finish around January 2030, more than three months after its registered date of September 2027.
Site inspections
20 August 2026
27%+5.5 pts
23 April 2026
22%+4.0 pts
29 January 2026
18%+8.4 pts
16 October 2025
9.2%+4.0 pts
18 June 2025
5.1%+5.1 pts
28 May 2024
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Mak Developers has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Mak I'Sola Bella?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Mak I'Sola Bella handover date?
- The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Mak I'Sola Bella?
- Mak I'Sola Bella was 27% built at the site inspection on 20 August 2026. The site has been inspected 6 times since May 2024. The Land Department took 34 site photos at its inspections.
- Is Mak I'Sola Bella delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
- Who is building Mak I'Sola Bella?
- The registered developer is Mak Developers. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Mak I'Sola Bella?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Saddlewood ParkAlso by Mak Developers. 12%, Due September 2027.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)







.jpg&w=3840&q=75)