Mak I'Sola Bella construction progress

Mak I'Sola Bella in Jumeirah Village Circle is 27% built at the Land Department inspection of August 2026. Developer Mak Developers. Completion registered for September 2027.

27%

Built, at the Land Department site inspection of 20 August 2026

Running behind its date

Completion date (Land Department)
September 2027
Finish at recent pace
January 2030
Construction started
September 2024
Registered with the Land Department
September 2024
Developer
Mak Developers
Units
207
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ماك إيسولا بيلا
Land Department project number
3096
Land Department site inspections
6

Schedule

Between October 2025 and August 2026 the site added about 1.8 points a month. At that rate it would finish around January 2030, more than three months after the September 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

20 August 2026

27%+5.5 pts

  • Mak I'Sola Bella construction site, Land Department inspection photo 1, 20 August 2026
  • Mak I'Sola Bella construction site, Land Department inspection photo 2, 20 August 2026
  • Mak I'Sola Bella construction site, Land Department inspection photo 3, 20 August 2026
  • Mak I'Sola Bella construction site, Land Department inspection photo 4, 20 August 2026

23 April 2026

22%+4.0 pts

  • Mak I'Sola Bella construction site, Land Department inspection photo 1, 23 April 2026
  • Mak I'Sola Bella construction site, Land Department inspection photo 2, 23 April 2026
  • Mak I'Sola Bella construction site, Land Department inspection photo 3, 23 April 2026
  • Mak I'Sola Bella construction site, Land Department inspection photo 4, 23 April 2026

29 January 2026

18%+8.4 pts

  • Mak I'Sola Bella construction site, Land Department inspection photo 1, 29 January 2026
  • Mak I'Sola Bella construction site, Land Department inspection photo 2, 29 January 2026
  • Mak I'Sola Bella construction site, Land Department inspection photo 3, 29 January 2026
  • Mak I'Sola Bella construction site, Land Department inspection photo 4, 29 January 2026

16 October 2025

9.2%+4.0 pts

  • Mak I'Sola Bella construction site, Land Department inspection photo 1, 16 October 2025
  • Mak I'Sola Bella construction site, Land Department inspection photo 2, 16 October 2025
  • Mak I'Sola Bella construction site, Land Department inspection photo 3, 16 October 2025
  • Mak I'Sola Bella construction site, Land Department inspection photo 4, 16 October 2025

18 June 2025

5.1%+5.1 pts

  • Mak I'Sola Bella construction site, Land Department inspection photo 1, 18 June 2025
  • Mak I'Sola Bella construction site, Land Department inspection photo 2, 18 June 2025
  • Mak I'Sola Bella construction site, Land Department inspection photo 3, 18 June 2025
  • Mak I'Sola Bella construction site, Land Department inspection photo 4, 18 June 2025

28 May 2024

0%

  • Mak I'Sola Bella construction site, Land Department inspection photo 1, 28 May 2024

All 34 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Mak Developers has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Mak I'Sola Bella?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Mak I'Sola Bella be completed?
The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around January 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Mak I'Sola Bella is built?
27%, measured at the Land Department site inspection on 20 August 2026. The Land Department engineers have inspected the site 6 times since May 2024.
Is Mak I'Sola Bella delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Mak I'Sola Bella?
The registered developer is Mak Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Mak I'Sola Bella?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.