Mak I'Sola Bella construction progress

The registered completion date for Mak I'Sola Bella in Jumeirah Village Circle is September 2027. At the last site inspection, in August 2026, it was 27% built. The developer is Mak Developers.

27%

Built, at the site inspection of 20 August 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
January 2030
Construction started
September 2024
First registered
September 2024
Developer
Mak Developers
Units
207
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ماك إيسولا بيلا
Project number
3096
Site inspections
6

Schedule

Between October 2025 and August 2026 the site added about 1.8 points a month. At that rate it would finish around January 2030, more than three months after its registered date of September 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 August 2026

27%+5.5 pts

  • Mak I'Sola Bella construction site, inspection photo 1, 20 August 2026
  • Mak I'Sola Bella construction site, inspection photo 2, 20 August 2026
  • Mak I'Sola Bella construction site, inspection photo 3, 20 August 2026
  • Mak I'Sola Bella construction site, inspection photo 4, 20 August 2026

23 April 2026

22%+4.0 pts

  • Mak I'Sola Bella construction site, inspection photo 1, 23 April 2026
  • Mak I'Sola Bella construction site, inspection photo 2, 23 April 2026
  • Mak I'Sola Bella construction site, inspection photo 3, 23 April 2026
  • Mak I'Sola Bella construction site, inspection photo 4, 23 April 2026

29 January 2026

18%+8.4 pts

  • Mak I'Sola Bella construction site, inspection photo 1, 29 January 2026
  • Mak I'Sola Bella construction site, inspection photo 2, 29 January 2026
  • Mak I'Sola Bella construction site, inspection photo 3, 29 January 2026
  • Mak I'Sola Bella construction site, inspection photo 4, 29 January 2026

16 October 2025

9.2%+4.0 pts

  • Mak I'Sola Bella construction site, inspection photo 1, 16 October 2025
  • Mak I'Sola Bella construction site, inspection photo 2, 16 October 2025
  • Mak I'Sola Bella construction site, inspection photo 3, 16 October 2025
  • Mak I'Sola Bella construction site, inspection photo 4, 16 October 2025

18 June 2025

5.1%+5.1 pts

  • Mak I'Sola Bella construction site, inspection photo 1, 18 June 2025
  • Mak I'Sola Bella construction site, inspection photo 2, 18 June 2025
  • Mak I'Sola Bella construction site, inspection photo 3, 18 June 2025
  • Mak I'Sola Bella construction site, inspection photo 4, 18 June 2025

28 May 2024

0%

  • Mak I'Sola Bella construction site, inspection photo 1, 28 May 2024

All 34 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Mak Developers has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Mak I'Sola Bella?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Mak I'Sola Bella handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Mak I'Sola Bella?
Mak I'Sola Bella was 27% built at the site inspection on 20 August 2026. The site has been inspected 6 times since May 2024. The Land Department took 34 site photos at its inspections.
Is Mak I'Sola Bella delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Mak I'Sola Bella?
The registered developer is Mak Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Mak I'Sola Bella?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.