Mak I'Sola Bella construction photos

34 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Mak I'Sola Bella was built on the day of each visit.

20 August 202627% built

23 April 202622% built

29 January 202618% built

16 October 20259.2% built

18 June 20255.1% built

28 May 20240% built

Back to Mak I'Sola Bella construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.