Saddlewood Park construction progress

The registered completion date for Saddlewood Park in Meydan Racecourse Community is September 2027. At the last site inspection, in August 2026, it was 12% built. The developer is Mak Developers.

12%

Built, at the site inspection of 24 August 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
April 2033
Construction started
December 2025
First registered
September 2025
Developer
Mak Developers
Units
62
Escrow bank
Sharjah Islamic Bank
Name in Arabic
سادلوود بارك
Project number
3889
Site inspections
3

Schedule

Between September 2025 and August 2026 the site added about 1.1 points a month. At that rate it would finish around April 2033, more than three months after its registered date of September 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 August 2026

12%+12 pts

  • Saddlewood Park construction site, inspection photo 1, 24 August 2026
  • Saddlewood Park construction site, inspection photo 2, 24 August 2026
  • Saddlewood Park construction site, inspection photo 3, 24 August 2026
  • Saddlewood Park construction site, inspection photo 4, 24 August 2026

14 April 2026

0.1%+0.1 pts

  • Saddlewood Park construction site, inspection photo 1, 14 April 2026
  • Saddlewood Park construction site, inspection photo 2, 14 April 2026
  • Saddlewood Park construction site, inspection photo 3, 14 April 2026
  • Saddlewood Park construction site, inspection photo 4, 14 April 2026

11 September 2025

0%

  • Saddlewood Park construction site, inspection photo 1, 11 September 2025
  • Saddlewood Park construction site, inspection photo 2, 11 September 2025

All 12 site photos, by inspection date

Context

Meydan Racecourse Community has 9 projects under construction, 31% built on average.

Mak Developers has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Saddlewood Park?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Saddlewood Park handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Saddlewood Park?
Saddlewood Park was 12% built at the site inspection on 24 August 2026. The site has been inspected 3 times since September 2025. The Land Department took 12 site photos at its inspections.
Is Saddlewood Park delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Saddlewood Park?
The registered developer is Mak Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Saddlewood Park?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.