Saddlewood Park construction progress
Saddlewood Park in Meydan Racecourse Community is 12% built at the Land Department inspection of August 2026. Developer Mak Developers. Completion registered for September 2027.
12%
Built, at the Land Department site inspection of 24 August 2026
Running behind its date
- Completion date (Land Department)
- September 2027
- Finish at recent pace
- April 2033
- Construction started
- December 2025
- Registered with the Land Department
- September 2025
- Developer
- Mak Developers
- Community
- Meydan Racecourse Community
- Units
- 62
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- سادلوود بارك
- Land Department project number
- 3889
- Land Department site inspections
- 3
Schedule
Between September 2025 and August 2026 the site added about 1.1 points a month. At that rate it would finish around April 2033, more than three months after the September 2027 date registered with the Land Department.
Site inspections
24 August 2026
12%+12 pts
14 April 2026
0.1%+0.1 pts
11 September 2025
0%
Context
Meydan Racecourse Community has 9 projects under construction, 31% built on average.
Mak Developers has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Saddlewood Park?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Saddlewood Park be completed?
- The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around April 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Saddlewood Park is built?
- 12%, measured at the Land Department site inspection on 24 August 2026. The Land Department engineers have inspected the site 3 times since September 2025.
- Is Saddlewood Park delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
- Who is building Saddlewood Park?
- The registered developer is Mak Developers. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Saddlewood Park?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Mak I'Sola BellaAlso by Mak Developers. 27%, Due September 2027.
- Royal ManorNearby in Meydan Racecourse Community. 78%, Due December 2018, passed.
- Tonino Lamborghini ResidencesNearby in Meydan Racecourse Community. 60%, Due December 2026.
- Emerge ResidencesNearby in Meydan Racecourse Community. 21%, Due November 2027.
- Mews MansionsNearby in Meydan Racecourse Community. 56%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.