Skip to content

Saddlewood Park construction progress

Saddlewood Park in Meydan Racecourse Community is 12% built at the Land Department inspection of August 2026. Developer Mak Developers. Completion registered for September 2027.

12%

Built, at the Land Department site inspection of 24 August 2026

Running behind its date

Completion date (Land Department)
September 2027
Finish at recent pace
April 2033
Construction started
December 2025
Registered with the Land Department
September 2025
Developer
Mak Developers
Units
62
Escrow bank
Sharjah Islamic Bank
Name in Arabic
سادلوود بارك
Land Department project number
3889
Land Department site inspections
3

Schedule

Between September 2025 and August 2026 the site added about 1.1 points a month. At that rate it would finish around April 2033, more than three months after the September 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

24 August 2026

12%+12 pts

  • Saddlewood Park construction site, Land Department inspection photo 1, 24 August 2026
  • Saddlewood Park construction site, Land Department inspection photo 2, 24 August 2026
  • Saddlewood Park construction site, Land Department inspection photo 3, 24 August 2026
  • Saddlewood Park construction site, Land Department inspection photo 4, 24 August 2026

14 April 2026

0.1%+0.1 pts

  • Saddlewood Park construction site, Land Department inspection photo 1, 14 April 2026
  • Saddlewood Park construction site, Land Department inspection photo 2, 14 April 2026
  • Saddlewood Park construction site, Land Department inspection photo 3, 14 April 2026
  • Saddlewood Park construction site, Land Department inspection photo 4, 14 April 2026

11 September 2025

0%

  • Saddlewood Park construction site, Land Department inspection photo 1, 11 September 2025
  • Saddlewood Park construction site, Land Department inspection photo 2, 11 September 2025

All 12 site photos, by inspection date

Context

Meydan Racecourse Community has 9 projects under construction, 31% built on average.

Mak Developers has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Saddlewood Park?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Saddlewood Park be completed?
The completion date registered with the Dubai Land Department is September 2027. At the pace of its recent inspections the site would reach 100% around April 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Saddlewood Park is built?
12%, measured at the Land Department site inspection on 24 August 2026. The Land Department engineers have inspected the site 3 times since September 2025.
Is Saddlewood Park delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Saddlewood Park?
The registered developer is Mak Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Saddlewood Park?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.