Saddlewood Park construction progress
The registered completion date for Saddlewood Park in Meydan Racecourse Community is September 2027. At the last site inspection, in August 2026, it was 12% built. The developer is Mak Developers.
12%
Built, at the site inspection of 24 August 2026
Running behind its date
- Registered completion date
- September 2027
- Finish at recent pace
- April 2033
- Construction started
- December 2025
- First registered
- September 2025
- Developer
- Mak Developers
- Community
- Meydan Racecourse Community
- Units
- 62
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- سادلوود بارك
- Project number
- 3889
- Site inspections
- 3
Schedule
Between September 2025 and August 2026 the site added about 1.1 points a month. At that rate it would finish around April 2033, more than three months after its registered date of September 2027.
Site inspections
24 August 2026
12%+12 pts
14 April 2026
0.1%+0.1 pts
11 September 2025
0%
Context
Meydan Racecourse Community has 9 projects under construction, 31% built on average.
Mak Developers has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Saddlewood Park?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Saddlewood Park handover date?
- The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Saddlewood Park?
- Saddlewood Park was 12% built at the site inspection on 24 August 2026. The site has been inspected 3 times since September 2025. The Land Department took 12 site photos at its inspections.
- Is Saddlewood Park delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
- Who is building Saddlewood Park?
- The registered developer is Mak Developers. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Saddlewood Park?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Mak I'Sola BellaAlso by Mak Developers. 27%, Due September 2027.
- Royal ManorNearby in Meydan Racecourse Community. 78%, Due December 2018, passed.
- Tonino Lamborghini ResidencesNearby in Meydan Racecourse Community. 60%, Due December 2026.
- Emerge ResidencesNearby in Meydan Racecourse Community. 21%, Due November 2027.
- Mews MansionsNearby in Meydan Racecourse Community. 56%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)