Luma21 construction progress

The register lists Luma21 in Jumeirah Village Circle as complete, with a registered completion date of April 2023. Its last site inspection on record was in February 2023. The developer is Townx Real Estate Development.

100%

Built, at the site inspection of 22 February 2023

Construction complete

Registered completion date
April 2023
Construction started
July 2021
First registered
December 2021
Units
238
Escrow bank
Commercial Bank of Dubai
Name in Arabic
لوما 21
Project number
2327
Site inspections
5

Schedule

The register lists Luma21 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 February 2023

100%+14 pts

  • Luma21 construction site, inspection photo 1, 22 February 2023
  • Luma21 construction site, inspection photo 2, 22 February 2023
  • Luma21 construction site, inspection photo 3, 22 February 2023
  • Luma21 construction site, inspection photo 4, 22 February 2023

18 October 2022

86%+31 pts

  • Luma21 construction site, inspection photo 1, 18 October 2022
  • Luma21 construction site, inspection photo 2, 18 October 2022
  • Luma21 construction site, inspection photo 3, 18 October 2022
  • Luma21 construction site, inspection photo 4, 18 October 2022

15 June 2022

55%+20 pts

  • Luma21 construction site, inspection photo 1, 15 June 2022
  • Luma21 construction site, inspection photo 2, 15 June 2022
  • Luma21 construction site, inspection photo 3, 15 June 2022
  • Luma21 construction site, inspection photo 4, 15 June 2022

22 March 2022

35%+25 pts

  • Luma21 construction site, inspection photo 1, 22 March 2022
  • Luma21 construction site, inspection photo 2, 22 March 2022
  • Luma21 construction site, inspection photo 3, 22 March 2022
  • Luma21 construction site, inspection photo 4, 22 March 2022

6 December 2021

10%

  • Luma21 construction site, inspection photo 1, 6 December 2021
  • Luma21 construction site, inspection photo 2, 6 December 2021
  • Luma21 construction site, inspection photo 3, 6 December 2021
  • Luma21 construction site, inspection photo 4, 6 December 2021

All 53 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Townx Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Luma21?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Luma21 handover date?
Construction of Luma21 is recorded as complete, with a registered completion date of April 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Luma21?
Luma21 was 100% built at the site inspection on 22 February 2023. The site has been inspected 5 times since December 2021. The Land Department took 53 site photos at its inspections.
Is Luma21 delayed?
The register lists construction as complete.
Who is building Luma21?
The registered developer is Townx Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Luma21?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.