11 Hills Park construction progress
The registered completion date for 11 Hills Park in Dubai Science Park is March 2027. At the last site inspection, in April 2026, it was 80% built. The developer is Townx Real Estate Development.
80%
Built, at the site inspection of 30 April 2026
On pace for its date
- Registered completion date
- March 2027
- Finish at recent pace
- August 2026
- Construction started
- November 2024
- First registered
- November 2024
- Developer
- Townx Real Estate Development
- Community
- Dubai Science Park
- Units
- 571
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- هيلز بارك 11
- Project number
- 3324
- Site inspections
- 6
Schedule
Since May 2025 11 Hills Park has added about 5.4 points a month. That puts 100% around August 2026, within three months of its registered completion date of March 2027.
Site inspections
30 April 2026
80%+20 pts
22 January 2026
61%+20 pts
22 October 2025
41%+15 pts
22 July 2025
26%+9.1 pts
13 May 2025
17%+17 pts
15 October 2024
0%
Context
Dubai Science Park has 10 projects under construction, 43% built on average.
Townx Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in 11 Hills Park?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the 11 Hills Park handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on 11 Hills Park?
- 11 Hills Park was 80% built at the site inspection on 30 April 2026. The site has been inspected 6 times since October 2024. The Land Department took 47 site photos at its inspections.
- Is 11 Hills Park delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2027.
- Who is building 11 Hills Park?
- The registered developer is Townx Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for 11 Hills Park?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Ashley HillsAlso by Townx Real Estate Development. 74%, Due March 2027.
- Vincitore Aqua DimoreNearby in Dubai Science Park. 14%.
- Binghatti HillsNearby in Dubai Science Park. 90%.
- Vincitore Aqua FloraNearby in Dubai Science Park. 1.3%, Due June 2028.
- Empire LivingsNearby in Dubai Science Park. 13%, Due November 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)