Golden Wood Views 5 construction progress

Golden Wood Views 5 in Jumeirah Village Circle was registered to complete in October 2026 and is still under construction. At the last site inspection, in April 2026, it was 89% built. The developer is Golden Wood Real Estate Development.

89%

Built, at the site inspection of 25 April 2026

1 months past its registered completion date

Registered completion date
October 2026
Finish at recent pace
March 2027
Construction started
October 2022
First registered
March 2023
Developer
Golden Wood Real Estate Development
Units
161
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
غولدن وود فيوس 5
Project number
2539
Site inspections
8

Schedule

Golden Wood Views 5 was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 1.0 points a month. Kept at that rate, the site would reach 100% around March 2027.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 April 2026

89%+6.0 pts

  • Golden Wood Views 5 construction site, inspection photo 1, 25 April 2026
  • Golden Wood Views 5 construction site, inspection photo 2, 25 April 2026
  • Golden Wood Views 5 construction site, inspection photo 3, 25 April 2026
  • Golden Wood Views 5 construction site, inspection photo 4, 25 April 2026

27 October 2025

83%+5.7 pts

  • Golden Wood Views 5 construction site, inspection photo 1, 27 October 2025
  • Golden Wood Views 5 construction site, inspection photo 2, 27 October 2025
  • Golden Wood Views 5 construction site, inspection photo 3, 27 October 2025
  • Golden Wood Views 5 construction site, inspection photo 4, 27 October 2025

7 April 2025

77%+21 pts

  • Golden Wood Views 5 construction site, inspection photo 1, 7 April 2025
  • Golden Wood Views 5 construction site, inspection photo 2, 7 April 2025
  • Golden Wood Views 5 construction site, inspection photo 3, 7 April 2025
  • Golden Wood Views 5 construction site, inspection photo 4, 7 April 2025

4 October 2024

56%+20 pts

  • Golden Wood Views 5 construction site, inspection photo 1, 4 October 2024
  • Golden Wood Views 5 construction site, inspection photo 2, 4 October 2024
  • Golden Wood Views 5 construction site, inspection photo 3, 4 October 2024
  • Golden Wood Views 5 construction site, inspection photo 4, 4 October 2024

7 June 2024

36%+8.5 pts

  • Golden Wood Views 5 construction site, inspection photo 1, 7 June 2024
  • Golden Wood Views 5 construction site, inspection photo 2, 7 June 2024
  • Golden Wood Views 5 construction site, inspection photo 3, 7 June 2024
  • Golden Wood Views 5 construction site, inspection photo 4, 7 June 2024

3 March 2024

28%+13 pts

  • Golden Wood Views 5 construction site, inspection photo 1, 3 March 2024
  • Golden Wood Views 5 construction site, inspection photo 2, 3 March 2024
  • Golden Wood Views 5 construction site, inspection photo 3, 3 March 2024
  • Golden Wood Views 5 construction site, inspection photo 4, 3 March 2024

25 September 2023

14%+14 pts

  • Golden Wood Views 5 construction site, inspection photo 1, 25 September 2023
  • Golden Wood Views 5 construction site, inspection photo 2, 25 September 2023
  • Golden Wood Views 5 construction site, inspection photo 3, 25 September 2023
  • Golden Wood Views 5 construction site, inspection photo 4, 25 September 2023

5 January 2023

0.2%

  • Golden Wood Views 5 construction site, inspection photo 1, 5 January 2023
  • Golden Wood Views 5 construction site, inspection photo 2, 5 January 2023
  • Golden Wood Views 5 construction site, inspection photo 3, 5 January 2023
  • Golden Wood Views 5 construction site, inspection photo 4, 5 January 2023

All 52 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Golden Wood Real Estate Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Golden Wood Views 5?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Golden Wood Views 5 handover date?
The registered completion date was October 2026, and the register still lists Golden Wood Views 5 as under construction. At the pace of its recent inspections the site would reach 100% around March 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Golden Wood Views 5?
Golden Wood Views 5 was 89% built at the site inspection on 25 April 2026. The site has been inspected 8 times since January 2023. The Land Department took 52 site photos at its inspections.
Is Golden Wood Views 5 delayed?
Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
Who is building Golden Wood Views 5?
The registered developer is Golden Wood Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Golden Wood Views 5?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.