Golden Wood Views 5 construction photos

52 photos from 8 site inspections, newest first. The percentage is how much of Golden Wood Views 5 was built on the day of each visit.

25 April 202689% built

27 October 202583% built

7 April 202577% built

4 October 202456% built

7 June 202436% built

3 March 202428% built

25 September 202314% built

5 January 20230.2% built

Back to Golden Wood Views 5 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.