Electra construction progress

No completion date is registered for Electra in Jumeirah Village Circle yet. At the last site inspection, in October 2026, it was 9.2% built. The developer is Acube Real Estate Development.

9.2%

Built, at the site inspection of 19 October 2026

Finish at recent pace
February 2048
Construction started
April 2024
First registered
May 2024
Developer
Acube Real Estate Development
Units
281
Escrow bank
Dubai Islamic Bank
Name in Arabic
اليكترا
Project number
2881
Site inspections
8

Schedule

Since March 2026 Electra has added about 0.4 points a month. At that rate the site reaches 100% around February 2048. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

19 October 2026

9.2%+1.4 pts

  • Electra construction site, inspection photo 1, 19 October 2026
  • Electra construction site, inspection photo 2, 19 October 2026
  • Electra construction site, inspection photo 3, 19 October 2026
  • Electra construction site, inspection photo 4, 19 October 2026

6 July 2026

7.9%+0.3 pts

  • Electra construction site, inspection photo 1, 6 July 2026
  • Electra construction site, inspection photo 2, 6 July 2026
  • Electra construction site, inspection photo 3, 6 July 2026
  • Electra construction site, inspection photo 4, 6 July 2026

21 May 2026

7.6%+0.9 pts

  • Electra construction site, inspection photo 1, 21 May 2026
  • Electra construction site, inspection photo 2, 21 May 2026
  • Electra construction site, inspection photo 3, 21 May 2026
  • Electra construction site, inspection photo 4, 21 May 2026

16 March 2026

6.7%+1.1 pts

  • Electra construction site, inspection photo 1, 16 March 2026
  • Electra construction site, inspection photo 2, 16 March 2026
  • Electra construction site, inspection photo 3, 16 March 2026
  • Electra construction site, inspection photo 4, 16 March 2026

17 July 2025

5.6%+0.7 pts

  • Electra construction site, inspection photo 1, 17 July 2025
  • Electra construction site, inspection photo 2, 17 July 2025
  • Electra construction site, inspection photo 3, 17 July 2025

2 April 2025

4.9%+4.6 pts

  • Electra construction site, inspection photo 1, 2 April 2025
  • Electra construction site, inspection photo 2, 2 April 2025
  • Electra construction site, inspection photo 3, 2 April 2025
  • Electra construction site, inspection photo 4, 2 April 2025

14 November 2024

0.3%+0.3 pts

  • Electra construction site, inspection photo 1, 14 November 2024
  • Electra construction site, inspection photo 2, 14 November 2024
  • Electra construction site, inspection photo 3, 14 November 2024
  • Electra construction site, inspection photo 4, 14 November 2024

4 April 2024

0%

  • Electra construction site, inspection photo 1, 4 April 2024
  • Electra construction site, inspection photo 2, 4 April 2024
  • Electra construction site, inspection photo 3, 4 April 2024

All 37 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Acube Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Electra?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Electra handover date?
No completion date is on record for Electra yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Electra?
Electra was 9.2% built at the site inspection on 19 October 2026. The site has been inspected 8 times since April 2024. The Land Department took 37 site photos at its inspections.
Who is building Electra?
The registered developer is Acube Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Electra?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.