Blossom 76 By Tranquil construction progress
The registered completion date for Blossom 76 By Tranquil in Jumeirah Village Circle is March 2027. At the last site inspection, in November 2026, it was 51% built. The developer is Tranquil Infra Developers.
51%
Built, at the site inspection of 18 November 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- February 2028
- Construction started
- August 2024
- First registered
- November 2024
- Developer
- Tranquil Infra Developers
- Community
- Jumeirah Village Circle
- Units
- 113
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- بلوسم 76 من ترانقويل
- Project number
- 3113
- Site inspections
- 9
Schedule
Between February 2026 and November 2026 the site added about 3.2 points a month. At that rate it would finish around February 2028, more than three months after its registered date of March 2027.
Site inspections
18 November 2026
51%+11 pts
14 August 2026
40%+6.0 pts
12 May 2026
34%+13 pts
5 February 2026
21%+6.4 pts
6 November 2025
15%+6.2 pts
26 August 2025
8.4%+2.4 pts
22 May 2025
6.0%+1.4 pts
17 April 2025
4.5%+4.5 pts
19 June 2024
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Tranquil Infra Developers has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Blossom 76 By Tranquil?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Blossom 76 By Tranquil handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Blossom 76 By Tranquil?
- Blossom 76 By Tranquil was 51% built at the site inspection on 18 November 2026. The site has been inspected 9 times since June 2024. The Land Department took 48 site photos at its inspections.
- Is Blossom 76 By Tranquil delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Blossom 76 By Tranquil?
- The registered developer is Tranquil Infra Developers. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Blossom 76 By Tranquil?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Blossom 40Also by Tranquil Infra Developers. 0%, Due March 2028.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)