Blossom 76 By Tranquil construction progress

The registered completion date for Blossom 76 By Tranquil in Jumeirah Village Circle is March 2027. At the last site inspection, in November 2026, it was 51% built. The developer is Tranquil Infra Developers.

51%

Built, at the site inspection of 18 November 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
February 2028
Construction started
August 2024
First registered
November 2024
Developer
Tranquil Infra Developers
Units
113
Escrow bank
Dubai Islamic Bank
Name in Arabic
بلوسم 76 من ترانقويل
Project number
3113
Site inspections
9

Schedule

Between February 2026 and November 2026 the site added about 3.2 points a month. At that rate it would finish around February 2028, more than three months after its registered date of March 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 November 2026

51%+11 pts

  • Blossom 76 By Tranquil construction site, inspection photo 1, 18 November 2026
  • Blossom 76 By Tranquil construction site, inspection photo 2, 18 November 2026
  • Blossom 76 By Tranquil construction site, inspection photo 3, 18 November 2026
  • Blossom 76 By Tranquil construction site, inspection photo 4, 18 November 2026

14 August 2026

40%+6.0 pts

  • Blossom 76 By Tranquil construction site, inspection photo 1, 14 August 2026
  • Blossom 76 By Tranquil construction site, inspection photo 2, 14 August 2026
  • Blossom 76 By Tranquil construction site, inspection photo 3, 14 August 2026
  • Blossom 76 By Tranquil construction site, inspection photo 4, 14 August 2026

12 May 2026

34%+13 pts

  • Blossom 76 By Tranquil construction site, inspection photo 1, 12 May 2026
  • Blossom 76 By Tranquil construction site, inspection photo 2, 12 May 2026
  • Blossom 76 By Tranquil construction site, inspection photo 3, 12 May 2026
  • Blossom 76 By Tranquil construction site, inspection photo 4, 12 May 2026

5 February 2026

21%+6.4 pts

  • Blossom 76 By Tranquil construction site, inspection photo 1, 5 February 2026
  • Blossom 76 By Tranquil construction site, inspection photo 2, 5 February 2026
  • Blossom 76 By Tranquil construction site, inspection photo 3, 5 February 2026
  • Blossom 76 By Tranquil construction site, inspection photo 4, 5 February 2026

6 November 2025

15%+6.2 pts

  • Blossom 76 By Tranquil construction site, inspection photo 1, 6 November 2025
  • Blossom 76 By Tranquil construction site, inspection photo 2, 6 November 2025
  • Blossom 76 By Tranquil construction site, inspection photo 3, 6 November 2025

26 August 2025

8.4%+2.4 pts

  • Blossom 76 By Tranquil construction site, inspection photo 1, 26 August 2025
  • Blossom 76 By Tranquil construction site, inspection photo 2, 26 August 2025

22 May 2025

6.0%+1.4 pts

  • Blossom 76 By Tranquil construction site, inspection photo 1, 22 May 2025
  • Blossom 76 By Tranquil construction site, inspection photo 2, 22 May 2025
  • Blossom 76 By Tranquil construction site, inspection photo 3, 22 May 2025
  • Blossom 76 By Tranquil construction site, inspection photo 4, 22 May 2025

17 April 2025

4.5%+4.5 pts

  • Blossom 76 By Tranquil construction site, inspection photo 1, 17 April 2025
  • Blossom 76 By Tranquil construction site, inspection photo 2, 17 April 2025
  • Blossom 76 By Tranquil construction site, inspection photo 3, 17 April 2025
  • Blossom 76 By Tranquil construction site, inspection photo 4, 17 April 2025

19 June 2024

0%

  • Blossom 76 By Tranquil construction site, inspection photo 1, 19 June 2024
  • Blossom 76 By Tranquil construction site, inspection photo 2, 19 June 2024

All 48 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Tranquil Infra Developers has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Blossom 76 By Tranquil?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Blossom 76 By Tranquil handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Blossom 76 By Tranquil?
Blossom 76 By Tranquil was 51% built at the site inspection on 18 November 2026. The site has been inspected 9 times since June 2024. The Land Department took 48 site photos at its inspections.
Is Blossom 76 By Tranquil delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Blossom 76 By Tranquil?
The registered developer is Tranquil Infra Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Blossom 76 By Tranquil?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.