Blossom 76 By Tranquil construction photos

48 photos from 9 site inspections, newest first. The percentage is how much of Blossom 76 By Tranquil was built on the day of each visit.

18 November 202651% built

14 August 202640% built

12 May 202634% built

5 February 202621% built

6 November 202515% built

26 August 20258.4% built

22 May 20256.0% built

17 April 20254.5% built

19 June 20240% built

Back to Blossom 76 By Tranquil construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.