Blossom 76 By Tranquil construction photos
48 photos from 9 site inspections, newest first. The percentage is how much of Blossom 76 By Tranquil was built on the day of each visit.
18 November 202651% built
14 August 202640% built
12 May 202634% built
5 February 202621% built
6 November 202515% built
26 August 20258.4% built
22 May 20256.0% built
17 April 20254.5% built
19 June 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.