Blossom 40 construction progress

The registered completion date for Blossom 40 is March 2028. At the last site inspection, in September 2026, it was 0% built. The developer is Tranquil Infra Developers.

0%

Built, at the site inspection of 10 September 2026

Running behind its date

Registered completion date
March 2028
Finish at recent pace
January 4134
Construction started
February 2026
First registered
December 2025
Developer
Tranquil Infra Developers
Units
66
Escrow bank
Dubai Islamic Bank
Name in Arabic
بلوسوم 40
Project number
4205
Site inspections
3

Schedule

Between November 2025 and September 2026 the site added about 0.0 points a month. At that rate it would finish around January 4134, more than three months after its registered date of March 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 September 2026

0%+0.0 pts

  • Blossom 40 construction site, inspection photo 1, 10 September 2026
  • Blossom 40 construction site, inspection photo 2, 10 September 2026
  • Blossom 40 construction site, inspection photo 3, 10 September 2026
  • Blossom 40 construction site, inspection photo 4, 10 September 2026

4 June 2026

0%

  • Blossom 40 construction site, inspection photo 1, 4 June 2026
  • Blossom 40 construction site, inspection photo 2, 4 June 2026

6 November 2025

0%

  • Blossom 40 construction site, inspection photo 1, 6 November 2025
  • Blossom 40 construction site, inspection photo 2, 6 November 2025

All 8 site photos, by inspection date

Context

Tranquil Infra Developers has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Blossom 40?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Blossom 40 handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 4134. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Blossom 40?
Blossom 40 was 0% built at the site inspection on 10 September 2026. The site has been inspected 3 times since November 2025. The Land Department took 8 site photos at its inspections.
Is Blossom 40 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Blossom 40?
The registered developer is Tranquil Infra Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Blossom 40?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.