Aura By Grovy construction progress

The register lists Aura By Grovy in Jumeirah Village Circle as complete, with a registered completion date of August 2024. Its last site inspection on record was in May 2025. The developer is Grovy Homes Real Estate Development.

100%

Built, at the site inspection of 30 May 2025

Construction complete

Registered completion date
August 2024
Construction started
May 2022
First registered
January 2023
Units
151
Escrow bank
Bank of Baroda
Name in Arabic
أورا من جروفي
Project number
2440
Site inspections
7

Schedule

The register lists Aura By Grovy as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 May 2025

100%+30 pts

  • Aura By Grovy construction site, inspection photo 1, 30 May 2025
  • Aura By Grovy construction site, inspection photo 2, 30 May 2025
  • Aura By Grovy construction site, inspection photo 3, 30 May 2025
  • Aura By Grovy construction site, inspection photo 4, 30 May 2025

4 June 2024

70%+16 pts

  • Aura By Grovy construction site, inspection photo 1, 4 June 2024
  • Aura By Grovy construction site, inspection photo 2, 4 June 2024
  • Aura By Grovy construction site, inspection photo 3, 4 June 2024
  • Aura By Grovy construction site, inspection photo 4, 4 June 2024

12 March 2024

55%+24 pts

  • Aura By Grovy construction site, inspection photo 1, 12 March 2024
  • Aura By Grovy construction site, inspection photo 2, 12 March 2024
  • Aura By Grovy construction site, inspection photo 3, 12 March 2024
  • Aura By Grovy construction site, inspection photo 4, 12 March 2024

30 October 2023

30%+13 pts

  • Aura By Grovy construction site, inspection photo 1, 30 October 2023
  • Aura By Grovy construction site, inspection photo 2, 30 October 2023
  • Aura By Grovy construction site, inspection photo 3, 30 October 2023
  • Aura By Grovy construction site, inspection photo 4, 30 October 2023

14 July 2023

17%+7.4 pts

  • Aura By Grovy construction site, inspection photo 1, 14 July 2023
  • Aura By Grovy construction site, inspection photo 2, 14 July 2023
  • Aura By Grovy construction site, inspection photo 3, 14 July 2023
  • Aura By Grovy construction site, inspection photo 4, 14 July 2023

4 April 2023

9.4%+5.7 pts

  • Aura By Grovy construction site, inspection photo 1, 4 April 2023
  • Aura By Grovy construction site, inspection photo 2, 4 April 2023
  • Aura By Grovy construction site, inspection photo 3, 4 April 2023
  • Aura By Grovy construction site, inspection photo 4, 4 April 2023

21 November 2022

3.8%

  • Aura By Grovy construction site, inspection photo 1, 21 November 2022
  • Aura By Grovy construction site, inspection photo 2, 21 November 2022
  • Aura By Grovy construction site, inspection photo 3, 21 November 2022

All 50 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Grovy Homes Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Aura By Grovy?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Aura By Grovy handover date?
Construction of Aura By Grovy is recorded as complete, with a registered completion date of August 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Aura By Grovy?
Aura By Grovy was 100% built at the site inspection on 30 May 2025. The site has been inspected 7 times since November 2022. The Land Department took 50 site photos at its inspections.
Is Aura By Grovy delayed?
The register lists construction as complete.
Who is building Aura By Grovy?
The registered developer is Grovy Homes Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Aura By Grovy?
Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.