Coral Isle Residences construction progress

The registered completion date for Coral Isle Residences in Palm Deira is March 2027. At the last site inspection, in August 2026, it was 7.2% built. The developer is Grovy Homes Real Estate Development.

7.2%

Built, at the site inspection of 17 August 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
August 2033
Construction started
April 2025
First registered
May 2025
Developer
Grovy Homes Real Estate Development
Community
Palm Deira
Units
68
Escrow bank
Zand Bank
Name in Arabic
كورال آيل ريزيدنس
Project number
3322
Site inspections
3

Schedule

Between April 2026 and August 2026 the site added about 1.1 points a month. At that rate it would finish around August 2033, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 August 2026

7.2%+5.0 pts

  • Coral Isle Residences construction site, inspection photo 1, 17 August 2026
  • Coral Isle Residences construction site, inspection photo 2, 17 August 2026
  • Coral Isle Residences construction site, inspection photo 3, 17 August 2026
  • Coral Isle Residences construction site, inspection photo 4, 17 August 2026

1 April 2026

2.1%+2.1 pts

  • Coral Isle Residences construction site, inspection photo 1, 1 April 2026
  • Coral Isle Residences construction site, inspection photo 2, 1 April 2026
  • Coral Isle Residences construction site, inspection photo 3, 1 April 2026

4 February 2025

0%

  • Coral Isle Residences construction site, inspection photo 1, 4 February 2025
  • Coral Isle Residences construction site, inspection photo 2, 4 February 2025

All 11 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Grovy Homes Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Coral Isle Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Coral Isle Residences handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Coral Isle Residences?
Coral Isle Residences was 7.2% built at the site inspection on 17 August 2026. The site has been inspected 3 times since February 2025. The Land Department took 11 site photos at its inspections.
Is Coral Isle Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Coral Isle Residences?
The registered developer is Grovy Homes Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Coral Isle Residences?
Zand Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.